Project Description
South side of Briarfield Road from Marshall to ChestnutInstallation of a 5' sidewalk along Briarfield Road from Marshall to Chestnut.To improve and install access throughout the City to create a more sustainable and safe pedestrian atmosphere. To bring existing pedestrian access up to required federal standards. This increases pedestrian, multi-use, and disabled accessibility.
Project Manager
Ioana Verde
757.926.8314
verdeic@nnva.gov
Inspector
Mark Ulisse
757.933.2318
ulissemv@nnva.gov

How does this project serve Newport News’ citizens?
To improve access throughout the City to create a more sustainable, and safe pedestrian atmosphere.

Relationship to Comprehensive Plan Themes
  • Sustainable
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 03-Jun-2019 04-Apr-2024
100%
PE - PAA & Consultant Selection 03-Jun-2019 24-Aug-2020
100%
PE - Design 25-Aug-2020 04-Apr-2024
100%
PE - Environmental 01-Feb-2021 24-Apr-2023
100%
PE - Public Involvement 25-Apr-2023 30-Jun-2023
100%
Right of Way 05-Apr-2024 13-Jan-2026
57%
ROW - Land Acquisition 05-Apr-2024 13-Jan-2026
57%
ROW - Utility Relocation 05-Apr-2024 13-Jan-2026
57%
Construction 14-Jan-2026 18-Apr-2028
CA - Pre-Ad 14-Jan-2026 02-Feb-2026
CA - Advertisement 03-Feb-2026 16-Mar-2026
CA - Bid Date 17-Mar-2026 17-Mar-2026
CA - Construction Award 18-Mar-2026 21-Jul-2026
CA - CEI 22-Jul-2026 14-Dec-2027
CA - Construction 22-Jul-2026 14-Dec-2027
CA - Construction Closeout 15-Dec-2027 18-Apr-2028
Project Closeout 19-Apr-2028 26-Dec-2028
Scoping 25-Apr-2023 12-Jun-2023
100%
PE/Design 03-Jun-2019 04-Apr-2024
100%

Comments

VDOT NTP for RW Phase has been received on 4/04/2024. RW acquisitions are currently underway. 04/04/2024

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Design - WRA - 108980 Briarfield Sidewalk WHITMAN, REQUARDT AND ASSOC. LLP 06-Nov-2020 01-Dec-2021 $149,136.00 $148,712.47

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.