Schedule

Activity Start Finish % Complete
PE/Design 01-Jul-2027 03-Jul-2028
PE - Preliminary 01-Jul-2027 30-Jun-2028
PE - Design 03-Jul-2028 03-Jul-2028
PE - Environmental 03-Jul-2028 03-Jul-2028
PE - Public Involvement 03-Jul-2028 03-Jul-2028
Right of Way 03-Jul-2028 03-Jul-2028
ROW - Land Acquisition 03-Jul-2028 03-Jul-2028
ROW - Utility Relocation 03-Jul-2028 03-Jul-2028
Construction 04-Jul-2028 06-Feb-2030
CA - Pre-Ad 04-Jul-2028 24-Jul-2028
CA - Advertisement 25-Jul-2028 14-Aug-2028
CA - Bid Date 15-Aug-2028 15-Aug-2028
CA - Construction Award 16-Aug-2028 05-Sep-2028
CA - CEI 06-Sep-2028 06-Sep-2028
CA - Construction 07-Sep-2028 30-Jan-2030
CA - Construction Closeout 31-Jan-2030 06-Feb-2030
Project Closeout 07-Feb-2030 13-Feb-2030
PE - Scoping 03-Jul-2028 03-Jul-2028

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.