Project Description
To mill and pave the Treasurer's Annex Office in Denbigh.
Project Manager
Thomas Cheney
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 05-Nov-2018 05-Nov-2018
100%
PE - Preliminary 02-Nov-2018 02-Nov-2018
100%
PE - Design 03-Nov-2018 03-Nov-2018
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Scoping 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 04-Oct-2024 19-Jun-2025
74%
CA - Pre-Ad 06-Nov-2018 06-Nov-2018
100%
CA - Advertisement 07-Nov-2018 07-Nov-2018
100%
CA - Bid Date 08-Nov-2018 08-Nov-2018
100%
CA - Construction Award 04-Oct-2024 18-Apr-2025
97%
CA - CEI 21-Apr-2025 20-May-2025
CA - Construction 21-Apr-2025 20-May-2025
CA - Construction Closeout 21-May-2025 19-Jun-2025
Project Closeout 20-Jun-2025 20-Jun-2025

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.