Project Description
This project will design and reconstruct various pedestrian amenities such as sidewalk, crosswalks, pedestrian signals, lighting, etc. along Campbell Road from Bland Boulevard South to Warwick Boulevard with the purpose of creating a safe and ADA accessible pedestrian atmosphere.
Project Manager
Jennifer Butler
757-926-1582
butlerja@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Jul-2022 30-Jan-2026
77%
PE - PAA Execution/Consultant Selection 01-Jul-2022 18-Jan-2024
100%
PE - Design 19-Jan-2024 30-Jan-2026
60%
PE - Environmental 19-Mar-2024 28-Feb-2025
100%
PE - Public Involvement 21-Jan-2025 19-Feb-2025
100%
Right of Way 31-Jan-2026 30-Jan-2027
ROW - Land Acquisition 31-Jan-2026 30-Jan-2027
ROW - Utility Relocation 31-Jan-2026 30-Jan-2027
Construction 31-Jan-2027 29-Jul-2028
CA - Pre-Ad 31-Jan-2027 01-Mar-2027
CA - Advertisement 02-Mar-2027 31-Mar-2027
CA - Bid Date 01-Apr-2027 01-Apr-2027
CA - Construction Award 02-Apr-2027 01-May-2027
CA - CEI 02-May-2027 30-May-2028
CA - Construction 02-May-2027 30-Apr-2028
CA - Construction Closeout 01-May-2028 29-Jul-2028
Project Closeout 30-Jul-2028 26-Nov-2028
PE - Scoping 25-Aug-2024 28-Feb-2025
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
UPC 117133 Campbell Rd Sidewalk Bland South to Warwick - Volkert Design Volkert, Inc. 18-Jan-2024 30-Jun-2025 $368,462.05 $278,486.94

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.