Project Description
Pump Station 127 has a wet well that is in poor condition. The wet walls are degraded with exposed aggregate and soft spots, vent fans are rotted, ladder and aluminum grate are corroded. This project will repair the degraded structures and line the wet well. Location: 765 Brick Kiln Blvd
Project Manager
Wendy Royston
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 18-Jun-2025 13-Apr-2026
100%
PE - Preliminary 18-Jun-2025 14-Dec-2025
100%
PE - Design 15-Dec-2025 13-Apr-2026
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 13-Jul-2026 11-Mar-2027
CA - Pre-Ad 13-Jul-2026 11-Aug-2026
CA - Advertisement 12-Aug-2026 10-Sep-2026
CA - Bid Date 11-Sep-2026 11-Sep-2026
CA - Construction Award 12-Sep-2026 11-Oct-2026
CA - CEI 12-Oct-2026 12-Oct-2026
CA - Construction 13-Oct-2026 09-Feb-2027
CA - Construction Closeout 10-Feb-2027 11-Mar-2027
Project Closeout 11-Apr-2027 24-Apr-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.