Project Description
Pump Station 127 has a wet well that is in poor condition. The wet walls are degraded with exposed aggregate and soft spots, vent fans are rotted, ladder and aluminum grate are corroded. This project will repair the degraded structures and line the wet well.
Project Manager
Wendy Royston
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 18-Jun-2025 16-Nov-2025
PE - Preliminary 18-Jun-2025 18-Aug-2025
PE - Design 19-Aug-2025 16-Nov-2025
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 15-Feb-2026 14-Oct-2026
CA - Pre-Ad 15-Feb-2026 16-Mar-2026
CA - Advertisement 17-Mar-2026 15-Apr-2026
CA - Bid Date 16-Apr-2026 16-Apr-2026
CA - Construction Award 17-Apr-2026 16-May-2026
CA - CEI 17-May-2026 17-May-2026
CA - Construction 18-May-2026 14-Sep-2026
CA - Construction Closeout 15-Sep-2026 14-Oct-2026
Project Closeout 14-Nov-2026 27-Nov-2026

Comments

Plan to start this project after PS065 wet well project is complete 02/07/2025

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.