Project Description
The project's initial scope is to repair and line existing sewers that connect the Patrick Henry Hospital, 1000 Old Denbigh Boulevard (and surrounding residences and businesses) to the Airport sewer system at Cherokee Drive. Investigation shows a large amount of groundwater infiltration into the 100 year old system. Location: 900 Bland Blvd
Project Manager
Landon Kee
757.926.8337
townecm@nnva.gov
Inspector

evertonjw@nnva.gov

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 05-May-2022 25-Nov-2023
100%
PE - Preliminary Engineering Report (WEST line) 05-May-2022 30-Dec-2022
100%
PE - Design 30-Mar-2023 25-Nov-2023
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 05-Apr-2024 22-May-2025
100%
CA - Pre-Ad 05-Apr-2024 10-Apr-2024
100%
CA - Advertisement 11-Apr-2024 09-May-2024
100%
CA - Bid Date 10-May-2024 10-May-2024
100%
CA - Construction Award 11-May-2024 30-May-2024
100%
CA - CEI 31-May-2024 31-Jul-2024
100%
CA - Construction Closeout 23-Apr-2025 22-May-2025
100%
Project Closeout 23-May-2025 16-Jul-2025
100%
CA - Construction 26-Aug-2024 22-Apr-2025
100%

Comments

Hospitals lines East & West are both complete. The warranty period has began for the west line project. 04/22/2025

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
AIRPORT COMPREHENSIVE SEWER PLAN - HOSPITAL SEWER LINE EAST PRISM CONTRACTORS & ENGINEERS INC 08-Nov-2021 08-Mar-2022 $224,672.00 $220,709.30
PER phase services: Airport Hospital Sewer Line WEST WHITMAN, REQUARDT AND ASSOC. LLP 05-May-2022 13-Jul-2022 $51,123.50 $46,189.70
AIRPORT COMPREHENSIVE SEWER PLAN - Hospital Sewer Line WEST (Design Services) WHITMAN, REQUARDT AND ASSOC. LLP 30-Mar-2023 26-Oct-2023 $56,348.00 $39,492.96
Airport Comprehensive Sewer Plan - Hospital Sewer Line West Rehabilitation PRISM CONTRACTORS & ENGINEERS INC 26-Aug-2024 21-Feb-2025 $632,763.00 $628,636.00
CA Services - Hospital Sewer Line West (WRA) WHITMAN, REQUARDT AND ASSOC. LLP 23-Jul-2024 31-May-2025 $30,116.00 $22,140.49

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.