Project Description
The stream behind the properties from 301 to 307 Warwick Landing Parkway is severely eroding. The channel needs to be stabilized through either a bank stabilization or a stream restoration. The project will improve stormwater runoff flow and area flood control and will increase aesthetics and reduce undesirable animal life. The City will be able to take credit for pollutant reduction (sediment, nitrogen, phosphorus) to the James River/Chesapeake Bay.
Project Manager
Juan Carlos Morgado Jofre
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 18-Oct-2021 31-Jan-2025
100%
PE - Preliminary 18-Oct-2021 01-Jan-2022
100%
PE - Design 02-Jan-2022 31-Jan-2025
100%
PE - Environmental 02-Apr-2022 07-Nov-2022
100%
PE - Public Involvement 07-Nov-2022 07-Nov-2022
100%
Right of Way 07-Nov-2022 31-Dec-2026
80%
ROW - Land Acquisition 27-Sep-2024 31-Dec-2026
64%
ROW - Utility Relocation 07-Nov-2022 07-Nov-2022
100%
Construction 01-Jan-2027 11-Apr-2028
CA - Pre-Ad 01-Jan-2027 10-Jan-2027
CA - Advertisement 11-Jan-2027 09-Feb-2027
CA - Bid Date 10-Feb-2027 10-Feb-2027
CA - Construction Award 11-Feb-2027 17-Mar-2027
CA - CEI 18-Mar-2027 18-Mar-2027
CA - Construction 19-Mar-2027 12-Jan-2028
CA - Construction Closeout 13-Jan-2028 11-Apr-2028
Project Closeout 12-Apr-2028 20-Jul-2028

Comments

The project is processing easement requests, while WSSI is preparing nutrient loads calculations for the SLAF program. 08/17/2025

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Warwick Landing Channel Improvemets Design MICHAEL BAKER INTERNATIONAL, INC 28-Mar-2022 21-Sep-2022 $194,163.00 $141,693.00
Nutrient calculations for Warwick Landing SLAF Application Wetlands Studies and Solutions, Inc. 11-Apr-2025 18-Apr-2025 $2,725.62 $2,069.70
Warwick Landing SLAF Application Process Wetlands Studies and Solutions, Inc. 24-Sep-2025 31-Dec-2025 $11,698.68 $11,694.92

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.