Project Description
The current ditches along Colberts Lane drain to the cul-de-sac at the end of the road. Currently the curb and gutter system on the cul-de-sac is higher than the ditch inverts, so the ditches do not drain. An adequate outfall will be designed and constructed for the drainage along Colberts Lane.
Project Manager
Khanh Khuu
Inspector

How does this project serve Newport News’ citizens?
TESTING

Relationship to Comprehensive Plan Themes
  • Sustainable
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 05-Nov-2018 31-Jan-2025
100%
PE - Preliminary 02-May-2022 30-Nov-2022
100%
PE - Design 01-Dec-2022 31-Jan-2025
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 31-Mar-2023 31-Jul-2026
93%
ROW - Land Acquisition 31-Mar-2023 16-Oct-2023
100%
ROW - Utility Relocation 01-Feb-2025 31-Jul-2026
85%
Construction 01-Aug-2026 30-Sep-2027
CA - Pre-Ad 01-Aug-2026 15-Aug-2026
CA - Advertisement 16-Aug-2026 04-Sep-2026
CA - Bid Date 05-Sep-2026 05-Sep-2026
CA - Construction Award 06-Sep-2026 20-Oct-2026
CA - CEI 21-Oct-2026 21-Oct-2026
CA - Construction 21-Oct-2026 22-Jul-2027
CA - Construction Closeout 23-Jul-2027 30-Sep-2027
Project Closeout 01-Oct-2027 29-Nov-2027

Comments

Reviewing the 100% plans to ensure all comments have been addressed and also preparing the bid document. However, we have not received an updated OPCC from Arcadis. They are working to reflect the current market. Preparing the bid document for Bryan and Kathie review next week. 5/1 - Sent the plans and the bid package to Bryan and Kathie to review. Bryan approved the plans and had some minor comments on the bid document. Pending from Kathie to review the plans and the bis package. 5/8 - All minor comments for the plan from Bryan and Kathie have been addressed and corrected. The plan is currently on Craig's desk for review and signature. 05/08/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Colbert's Lane Pre-Design Evaluation - Feasible Alternative Solutions Arcadis-U.s., INC. 06-Sep-2022 02-Dec-2022 $28,507.98 $28,507.98
Coberts Lane Drainage Improvements Arcadis-U.s., INC. 24-Feb-2023 08-Dec-2023 $217,064.78 $201,793.79

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.