Schedule

Activity Start Finish % Complete
PE/Design 02-Nov-2018 30-Jun-2028
77%
PE - Preliminary 02-Nov-2018 09-Aug-2021
100%
PE - Design 07-Jul-2021 30-Jun-2028
68%
PE - Environmental 01-Dec-2022 01-Jul-2024
100%
Right of Way 30-Apr-2022 30-Jun-2026
94%
ROW - Land Acquisition 03-Oct-2022 03-Oct-2023
100%
ROW - Utility Relocation 30-Apr-2022 30-Jun-2026
94%
Construction 01-Jul-2028 12-Apr-2030
CA - Pre-Ad 01-Jul-2028 14-Jul-2028
CA - Advertisement 15-Jul-2028 13-Aug-2028
CA - Bid Date 14-Aug-2028 14-Aug-2028
CA - Construction Award 15-Aug-2028 04-Sep-2028
CA - CEI 05-Sep-2028 04-Sep-2029
CA - Construction 05-Sep-2028 11-Feb-2030
CA - Construction Closeout 12-Feb-2030 12-Apr-2030
Project Closeout 13-Apr-2030 11-Jul-2030
PE - Design 30% 12-Jan-2022 29-Apr-2022
100%
PE - Design Concept 07-Jul-2021 10-Dec-2021
100%
PE - Concept Stakeholder Review 10-Dec-2021 12-Jan-2022
100%
PE - Pre-Final Submittal 15-Jun-2022 28-Oct-2022
100%
PE - Final / Prepare Bid Package 02-Jul-2024 30-Jun-2028
44%
PE - 30% Review 30-Apr-2022 29-May-2022
100%
PE - Pre-Final Review 29-Oct-2022 30-Nov-2022
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
ATCS - Ivy Avenue Road Reconstruction - Design ATCS, P.L.C 27-Jul-2021 31-Aug-2022 $930,338.10 $927,754.55
AWARD FOR RELOCATION/CONVERSION FROM OVERHEAD UTILITIES VIRGINIA ELECTRIC AND POWER COMPANY 11-Nov-2022 31-Dec-2023 $470,425.08 $0.00
Cox Comm - Ivy Ave - Undergrounding COX COMMUNICATIONS INC. 06-Oct-2023 31-Mar-2024 $352,390.97 $352,390.97
Verizon - Overhead Utilities Relocation VERIZON 28-Dec-2023 31-Dec-2024 $416,337.28 $0.00
Dominion Underground Utilities Phase 2 VIRGINIA ELECTRIC AND POWER COMPANY 14-Jun-2024 29-Dec-2024 $236,305.00 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.