Project Description
The Southeast Community Resource Area (SECRA) will be a 21st century one-stop shop that supports all residents, educates the mind, body and spirit, and creates a distinctive community gathering place. C. Waldo Scott Center-Mission: Provide HOPE to families, while developing the WHOLE CHILD. This is achieved by providing comprehensive services to educate and foster growth and development of youth and families. Pearl Bailey Library-Mission: We connect, inspire, enrich and empower. Huntington Middle School-Mission: Ensuring that all students graduate college, career and citizen-ready. Doris Miller Community Center-Mission: Te enhance the quality of life for the residents and visitors of the City of Newport News through the provision of quality recreational services, programs, and facilities.
Project Manager
Bruce Wobser
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 03-Mar-2022 15-Mar-2023
100%
PE - Preliminary 04-Mar-2022 15-Mar-2023
100%
PE - Design 04-Mar-2022 15-Mar-2023
100%
PE - Environmental 03-Mar-2022 15-Mar-2023
100%
PE - Public Involvement 03-Mar-2022 15-Mar-2023
100%
Right of Way 03-Mar-2022 15-Mar-2023
100%
ROW - Land Acquisition 03-Mar-2022 15-Mar-2023
100%
ROW - Utility Relocation 03-Mar-2022 15-Mar-2023
100%
Construction 09-Jan-2024 23-Jul-2026
92%
CA - Pre-Ad 09-Jan-2024 29-Feb-2024
100%
CA - Advertisement 01-Mar-2024 04-Apr-2024
100%
CA - Bid Date 12-Apr-2024 12-Apr-2024
100%
CA - Construction Award 13-Apr-2024 09-May-2024
100%
CA - CEI 03-May-2024 03-May-2024
100%
CA - Construction 03-May-2024 23-Jun-2026
94%
CA - Construction Closeout 24-Jun-2026 23-Jul-2026
Project Closeout 24-Jul-2026 19-Oct-2026

Comments

Substantial Completion - 06-23-2026 Final Completion - 6-23-2026 Change Order % - 2.9% CMU & brick work cont, adding door frames & storefront , Foundation work ongoing, Slabs are being poured, and underground utilities are ongoing, roof deck is being installed, steel is still being erected, mechanical pumps and water heaters installed, duct work has started, Steel still not complete. Contractor installed fireproof without substrate inspection Possible solution for the elevators control tx pad - Dominion advised tx to be delivered May 12. Working with schools to finalize FFE costs. We have received conditional approval for the phased approached to the BMP. Met with MEB to review project schedule. New schedule has a July 2027 completion. City reviewing schedule. City is set up the delay meeting for 5-11. 05/08/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
SECRA Master Planning QUINN EVANS ARCHITECTS, INC 16-Apr-2021 30-Nov-2021 $454,898.00 $26,952.82
SECRA Middle School Design Bid Package QUINN EVANS ARCHITECTS, INC 04-Mar-2022 31-Dec-2024 $4,338,358.50 $3,741,367.68
SECRA - Huntington Middle School MEB GENERAL CONTRACTORS, INC 03-Jun-2024 03-Feb-2026 $64,645,580.51 $36,533,482.90
SECRA - Huntington Middle School ESCROW MEB GENERAL CONTRACTORS, INC 03-Jun-2024 03-Feb-2026 $3,232,279.02 $1,835,370.76
HMS- MCDONOUGH BOLYARD PECK, INC. Newport News - Engineering 21-Feb-2025 30-Jun-2025 $12,144.00 $11,385.00
SECRA HUNTINGTON MIDDLE SCHOOL MCDONOUGH BOLYARD PECK, INC (MBP) 12-Feb-2026 31-Dec-2026 $30,322.24 $3,207.16
SECRA HUNTINGTON MIDDLE SCHOOL MCDONOUGH BOLYARD PECK, INC (MBP) 18-Feb-2026 27-Dec-2026 $2,915.60 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.