Project Description
Project will install sidewalk on both sides of Jefferson Avenue from Shields Road to Sea Pine Lane.  Amenities will also be installed at two (2) existing HRT Bus Stops as part of the project.
Project Manager
Jennifer Butler
757-926-1582
butlerja@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
ADA compliant pathways and crossings will improve safety within the corridor.

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
Project Closeout 22-Sep-2029 19-Jan-2030
PE/Design 01-Oct-2021 31-Jul-2026
100%
PE - Preliminary 01-Oct-2021 07-Nov-2022
100%
PE - Design 12-Jun-2023 31-Jul-2026
100%
PE - Environmental 30-Oct-2023 30-Sep-2025
100%
PE - Public Involvement 29-Apr-2025 17-Jun-2025
100%
Right of Way 01-Aug-2026 31-Jul-2028
5%
ROW - Utility Easements and Utility Relocation 01-Aug-2026 31-Jul-2028
5%
Construction 01-Aug-2028 21-Sep-2029
CA - Pre-Ad 03-Mar-2026 02-Jun-2026
100%
CA - Advertisement 01-Aug-2028 26-Aug-2028
CA - Bid Date 27-Aug-2028 27-Aug-2028
CA - Construction Award 28-Aug-2028 26-Sep-2028
CA - CEI 27-Sep-2028 23-Jul-2029
CA - Construction 27-Sep-2028 23-Jun-2029
CA - Construction Closeout 24-Jun-2029 21-Sep-2029
PE - Scoping 01-Oct-2024 29-Apr-2025
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Design Engineering Services JACOBS ENGINEERING GROUP, INC 12-Jun-2023 09-Mar-2026 $625,763.09 $345,356.60

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.