Project Description
This HSIP/BPSP funded project will provide sidewalk and drainage improvements to Harpersville Road from Bayberry Drive to Daphia Circle and is the third phase of sidewalk on Harpersville/Saunders.
Project Manager
Melaney Hollins
757-926-8314
hollinsmn@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
Project Closeout 30-Apr-2031 26-Oct-2031
PE/Design 01-Jul-2020 31-Oct-2026
94%
PE - Preliminary 01-Jul-2020 27-Mar-2023
100%
PE - Design 12-Jun-2023 31-Oct-2026
88%
PE - Environmental 11-Sep-2023 31-Dec-2025
100%
PE - Public Involvement 01-Jan-2026 31-Mar-2026
100%
Right of Way 01-Nov-2026 30-Oct-2028
ROW - Land Acquisition 01-Nov-2026 30-Oct-2028
ROW - Utility Relocation 01-Nov-2026 30-Oct-2028
Construction 28-Feb-2029 29-Apr-2031
CA - Pre-Ad 28-Feb-2029 29-Mar-2029
CA - Advertisement 30-Mar-2029 28-Apr-2029
CA - Bid Date 29-Apr-2029 29-Apr-2029
CA - Construction Award 30-Apr-2029 28-Jul-2029
CA - CEI 29-Jul-2029 29-Jan-2031
CA - Construction 29-Jul-2029 29-Jan-2031
CA - Construction Closeout 30-Jan-2031 29-Apr-2031
PE - Scoping 16-May-2025 30-Jun-2025
100%

Comments

90% Plans were submitted and internal review comments were provided to the designer. External VDOT comments will also be provided upon conclusion of their review. 05/22/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Design Engineering Services JACOBS ENGINEERING GROUP, INC 12-Jun-2023 09-Mar-2026 $713,423.70 $335,749.53

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.