Project Description
This project supports the build out of the City Center Parcels between Lakefront Commons and Town Center Drive. The scope includes left turn lanes for the two intersections, a new signal at Town Center Drive, signal modifications at Lakefront Commons, and other ancillary work.
Project Manager
Thomas Cheney
(757) 926-8715
cheneytc@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 23-May-2019 30-Sep-2021
100%
PE - Preliminary 23-May-2019 31-Oct-2019
100%
PE - Design 03-Jun-2019 30-Sep-2021
100%
PE - Environmental 31-May-2019 29-Nov-2019
100%
PE - Public Involvement 10-Sep-2019 01-Nov-2019
100%
Right of Way 14-Oct-2019 01-Dec-2022
100%
ROW - Utility Relocation 14-Oct-2019 01-Dec-2022
100%
Construction 20-Mar-2023 23-Jun-2025
100%
CA - Pre-Ad 20-Mar-2023 03-Apr-2023
100%
CA - Advertisement 07-Jun-2023 17-Jul-2023
100%
CA - Bid Date 18-Jul-2023 18-Jul-2023
100%
CA - Construction Award 19-Jul-2023 07-Aug-2023
100%
CA - CEI 16-Oct-2023 07-Apr-2025
100%
CA - Construction 16-Oct-2023 07-Apr-2025
100%
CA - Construction Closeout 08-Apr-2025 19-May-2025
100%
Project Closeout 20-May-2025 23-Jun-2025
100%
Land Acquisition 21-Oct-2019 30-Jun-2021
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
CCTIS - Lakefront Commons and Town Center Drive Improvements ATCS, P.L.C 20-Aug-2019 30-Nov-2020 $332,602.03 $327,842.22
Cox Communications Utility Relocation: CCTIS Lakefront and Town Center COX COMMUNICATIONS INC. 23-Jan-2020 23-May-2020 $308,042.55 $0.00
Verizon Virginia Utility Relocation: CCTIS Lakefront and Town Center VERIZON 29-Apr-2020 31-Jul-2020 $46,767.00 $30,696.55
CCTIS - Lakefront - NN Public Schools Fiber Relocation Newport News Public Schools 23-Apr-2020 11-Aug-2020 $14,059.73 $0.00
Waterworks Fiber Relocation: CCTIS Lakefront and Town Center Cable Associates Inc 14-Sep-2020 31-Dec-2020 $17,455.49 $6,506.92
CCTIS - Lakefront - SEGRA - LUMOS Utility Relocations Segra 24-Jul-2020 31-Dec-2020 $13,471.11 $0.00
CCTIS - Lakefront - Metro Fiber Utility Relocation Cable Associates Inc 21-Jul-2020 31-Dec-2020 $12,060.13 $12,060.13
CCTIS - Lakefront - Utility Relocations - Dominion Energy VIRGINIA ELECTRIC AND POWER COMPANY 09-Dec-2020 22-Mar-2021 $23,524.88 $23,524.88
CCTIS - Thimble Shoals - Utility Relocations - Cox Communications COX COMMUNICATIONS INC. 27-Jan-2020 31-May-2020 $81,304.20 $0.00
CCTIS - Thimble Shoals - Design Services ATCS, P.L.C 21-Aug-2019 20-Mar-2023 $154,341.00 $6,092.66
CCTIS - Lakefront Commons & Town Center Drive Improvements & Thimble Shoals Intersection Improvement Parkway Grading 16-Oct-2023 28-Apr-2024 $3,019,797.75 $2,680,540.40
CANON BLVD & THIMBLE SHOALS INSTERSECTION WORK: (1 VIRGINIA ELECTRIC AND POWER COMPANY 08-Jul-2024 30-Jun-2025 $1,924.55 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.