Project Description
Location:  Warwick Blvd from Raleigh to government ditchDescription:  Drainage improvements on Warwick Blvd from Raleigh Rd to the Government Ditch, with the storm sewer main along the south side of Warwick Blvd by connecting the majority of the existing system into the main storm sewer pipe and then out-falling into the government ditch.  Called Warwick Boulevard at Rivermont Phase I for funding purposes. Resurfacing and associated concrete repairs. Approximately 50 businesses and nearly 3,000 LF of roadway, along Warwick Boulevard, will benefit from the new storm water drainage system. The new system is designed to present storm water management standards and will be able to conduct runoff from smaller storm events.
Project Manager
Thomas Cheney
757.926.8715
cheneytc@nnva.gov
Inspector
Doug Walker
walkerDE@nnva.gov

How does this project serve Newport News’ citizens?
Reduced flooding risk and associated property damage.

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 11-Dec-2012 15-Nov-2023
100%
PE - Preliminary 11-Dec-2012 13-Jan-2013
100%
PE - Design 14-Jan-2013 12-Apr-2020
100%
PE - Environmental 03-Jan-2022 23-Nov-2022
100%
PE - Public Involvement 28-Oct-2020 10-Nov-2020
100%
Right of Way 18-Mar-2022 17-Jun-2023
100%
ROW - Land Acquisition 01-Feb-2023 17-Jun-2023
100%
ROW - Utility Relocation - Dominion Light Poles 18-Mar-2022 13-Oct-2022
100%
Construction 15-Nov-2023 09-Feb-2027
71%
CA - Pre-Ad 15-Nov-2023 25-Nov-2023
100%
CA - Advertisement 25-Nov-2023 18-Dec-2023
100%
CA - Bid Date 18-Dec-2023 18-Dec-2023
100%
CA - Construction Award 18-Dec-2023 10-Jan-2024
100%
CA - CEI 04-Mar-2024 26-Dec-2026
72%
CA - Construction 04-Mar-2024 26-Dec-2026
72%
CA - Construction Closeout 27-Dec-2026 09-Feb-2027
Project Closeout 10-Feb-2027 02-Mar-2027
Public Information presentation 28-Oct-2020 10-Nov-2020
100%
PE - Re-Design 07-May-2021 27-Oct-2022
100%
CA - 1st-Bid Date 07-Dec-2023 07-Dec-2023
100%
PE - Value Engineering 16-Apr-2021 01-May-2021
100%
PE - Corps of Engineers 408 Review / JPA 18-Jan-2022 15-Nov-2022
100%
PE - Prepare Bid Docs 16-Nov-2022 15-Nov-2023
100%

Comments

Project Completion expected Early 2027. 02/23/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
RK&K - Professional Services RUMMEL, KLEPPER & KAHL, LLP 18-Sep-2020 22-Dec-2022 $25,136.00 $17,965.93
Warwick Boulevard Drainage Improvements - Woolpert Value Engineeering Services WOOLPERT, INC. 16-Apr-2021 07-May-2021 $13,616.00 $11,121.00
RK&K - Redesign Outfall and Maintenance of Traffic Plan RUMMEL, KLEPPER & KAHL, LLP 30-Aug-2021 31-Aug-2022 $102,696.08 $102,696.08
Warwick Blvd Drainage - Dominion - Relocate Streetlights VIRGINIA ELECTRIC AND POWER COMPANY 08-Jun-2022 30-Nov-2022 $33,268.21 $33,268.21
NXL - Construction Estimate CENTURY ENGINEERING, INC 04-May-2023 26-May-2023 $6,458.60 $6,310.43
Warwick Boulevard Drainage Improvements - Basic BASIC CONSTRUCTION CO.,L.L.C 04-Mar-2024 14-Nov-2025 $10,862,614.74 $5,761,269.50
Warwick Blvd Drainage - QA Testing - Terracon GEOTECHNICAL ENVIRONMENTAL AND TESTING 01-Apr-2024 29-Dec-2025 $34,915.00 $5,235.00
Verizon - Relocate VERIZON 02-Jul-2024 29-Dec-2024 $23,008.90 $0.00
NXL - Inspection Services CENTURY ENGINEERING, INC 17-Nov-2025 31-Dec-2026 $376,796.89 $43,649.24

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.