Schedule

Activity Start Finish % Complete
PE/Design 16-Aug-2012 31-Dec-2026
94%
PE - Preliminary 16-Aug-2012 16-Aug-2012
100%
PE - Design 17-Aug-2012 15-May-2018
100%
PE - Environmental 07-Feb-2020 07-Feb-2020
100%
PE - Public Involvement 07-Feb-2020 07-Feb-2020
100%
Right of Way 08-Nov-2016 31-Dec-2026
92%
ROW - Land Acquisition 08-Nov-2016 31-Dec-2025
100%
ROW - Utility Relocation 14-Jun-2024 31-Dec-2026
71%
Construction 04-Jan-2027 30-Jan-2029
CA - Pre-Ad 04-Jan-2027 05-Feb-2027
CA - Advertisement 08-Feb-2027 05-Mar-2027
CA - Bid Date 08-Mar-2027 08-Mar-2027
CA - Construction Award 09-Mar-2027 02-Apr-2027
CA - CEI 05-Apr-2027 01-Nov-2028
CA - Construction 05-Apr-2027 02-Oct-2028
CA - Construction Closeout 03-Oct-2028 30-Jan-2029
Project Closeout 31-Jan-2029 01-May-2029
PE - Address CSX Comments 02-Mar-2023 30-Jun-2026
93%
PE - Design CSX Comments 19-Sep-2023 02-Sep-2024
100%
PE - Redesign Intersection Geometry 14-Jan-2026 31-Dec-2026
24%

Comments

The consultant is working to revise the design to address utility conflicts and signal modifications. 10/27/2025

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
CSX FOR ESCROW CSX Transportation $17,776.00 $9,169.17
Warwick Blvd and Yorktown Road - Design Revision JACOBS ENGINEERING GROUP, INC 19-Sep-2023 01-Sep-2024 $292,939.50 $173,561.70
CSX - PRELIMINARY ENGINEERING AGREEMENT CSX TRANSPORTATION INC 26-Mar-2026 30-Jun-2027 $43,173.00 $43,173.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.