Project Description
500 Bland Blvd to Sluice MillThis Phase of the Newport News Transportation Center will be the 2nd construction contract focusing on track work and the service facility.
Project Manager
Vincent Urbano
757.926.8694
vurbano@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
This project will provide a centralized multimodal transit facility for the City with important link

Relationship to Comprehensive Plan Themes
  • Accessible

Schedule

Activity Start Finish % Complete
PE/Design 15-Oct-2012 08-Jun-2017
100%
PE - Preliminary 15-Oct-2012 28-Nov-2012
100%
PE - Design 17-Dec-2012 08-Jun-2017
100%
PE - Environmental 13-Dec-2013 03-Feb-2016
100%
PE - Public Involvement 13-Dec-2013 03-Feb-2016
100%
Right of Way 19-Sep-2016 08-Jul-2018
100%
ROW - Land Acquisition 19-Sep-2016 07-Jun-2017
100%
ROW - Utility Relocation 15-Jan-2018 08-Jul-2018
100%
Construction 21-Jan-2020 30-Oct-2024
100%
CA - Pre-Ad 21-Jan-2020 02-Feb-2020
100%
CA - Advertisement 03-Feb-2020 21-Mar-2020
100%
CA - Bid Date 14-Apr-2020 14-Apr-2020
100%
CA - Construction Award 15-Apr-2020 17-Jun-2020
100%
CA - CEI 10-Dec-2020 22-May-2024
100%
CA - Construction 10-Dec-2020 30-Sep-2024
100%
CA - Construction Closeout 01-Oct-2024 30-Oct-2024
100%
Project Closeout 31-Oct-2024 29-Nov-2024
100%

Comments

awaiting repair of ACS system to obtain CO. 02/09/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Dominion Power WOR 10001769 CNN001 Utility relocations. VIRGINIA ELECTRIC AND POWER COMPANY 24-May-2019 30-Aug-2019 $337,055.59 $337,055.59
AT&T relocations CNN001 Newport News Transportation Center AT&T Corp 24-May-2019 30-Aug-2019 $128,858.54 $110,023.24
NNTC Trackwork and Service Facility CNN001 - Sprint relocations in CSX R/W Sprint 22-Aug-2019 31-Oct-2019 $331,258.02 $331,258.02
CNN0001 - Construction Inspection and Administration A. Morton Thomas & Associates Inc. 14-Nov-2019 14-Nov-2022 $2,295,285.42 $2,258,955.52
UPC CNN001 WSP Engineer of Record Services WSP USA, INC. 14-Nov-2019 14-Nov-2022 $144,880.81 $144,880.81
UPC CNN0001 Trackwork and Service Facility ALLAN MYERS VA, INC. 10-Dec-2020 03-Apr-2022 $13,990,494.39 $13,249,736.29
CSX Flagging and tie in construction CSX Transportation 29-Jun-2020 01-Jul-2022 $1,434,428.05 $1,362,833.32
AT&T design services AT&T Corp 13-Oct-2017 03-Jun-2023 $6,000.00 $0.00
Liquidated Damages Newport News - Engineering $1,643,750.00 $0.00
CSX amendment no 1 CSX TRANSPORTATION INC 01-Jun-2023 18-Dec-2023 $1,307,007.00 $970,364.21
Dominion Power service for streetlights on Warwick Springs Drive WR 10430472 VIRGINIA ELECTRIC AND POWER COMPANY 26-May-2023 31-May-2023 $6,716.53 $6,716.53
Electrical service for Building at Service facility- DOM WR 10430470 VIRGINIA ELECTRIC AND POWER COMPANY 15-Jun-2023 12-Sep-2023 $20,434.25 $20,434.25
Cox Communications Fiber service to Service Facility COX COMMUNICATIONS INC. 06-Oct-2023 12-Dec-2023 $63,191.00 $61,191.00
Cranemasters Inc Newport News - Engineering 15-Jul-2024 17-Jul-2024 $2,737.00 $0.00
Platform Sign lowering CENTENNIAL CONTRACTORS ENTERPRISES, INC 13-Feb-2025 30-Jun-2025 $32,776.69 $32,776.69
Johnson Controls installation of Main ACS Board Newport News - Engineering 31-Jan-2026 20-Feb-2026 $4,310.46 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.