Project Description
500 Bland Blvd to Sluice MillThis Phase of the Newport News Transportation Center will be the 2nd construction contract focusing on track work and the service facility.
Project Manager
Vincent Urbano
757.926.8694
vurbano@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
This project will provide a centralized multimodal transit facility for the City with important link

Relationship to Comprehensive Plan Themes
  • Accessible

Schedule

Activity Start Finish % Complete
PE/Design 15-Oct-2012 08-Jun-2017
100%
PE - Preliminary 15-Oct-2012 28-Nov-2012
100%
PE - Design 17-Dec-2012 08-Jun-2017
100%
PE - Environmental 13-Dec-2013 03-Feb-2016
100%
PE - Public Involvement 13-Dec-2013 03-Feb-2016
100%
Right of Way 19-Sep-2016 08-Jul-2018
100%
ROW - Land Acquisition 19-Sep-2016 07-Jun-2017
100%
ROW - Utility Relocation 15-Jan-2018 08-Jul-2018
100%
Construction 21-Jan-2020 01-Aug-2022
96%
CA - Pre-Ad 21-Jan-2020 02-Feb-2020
100%
CA - Advertisement 03-Feb-2020 21-Mar-2020
100%
CA - Bid Date 14-Apr-2020 14-Apr-2020
100%
CA - Construction Award 15-Apr-2020 17-Jun-2020
100%
CA - CEI 10-Dec-2020 01-Aug-2022
94%
CA - Construction 10-Dec-2020 03-Apr-2022
100%
CA - Construction Closeout 04-Apr-2022 01-Aug-2022
74%
Project Closeout 02-Aug-2022 23-Aug-2022

Comments

Crash wall is complete. 06/29/2022

excavating for crashwall and constructing Soil nail wall.  05/23/2022

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Dominion Power WOR 10001769 CNN001 Utility relocations. Dominion Energy 24-May-2019 30-Aug-2019 $123,773.51 $0.00
AT&T relocations CNN001 Newport News Transportation Center AT&T Corp 24-May-2019 30-Aug-2019 $128,858.54 $110,023.24
NNTC Trackwork and Service Facility CNN001 - Sprint relocations in CSX R/W Sprint 22-Aug-2019 31-Oct-2019 $331,258.02 $331,258.02
CNN0001 - Construction Inspection and Administration A. Morton Thomas & Associates Inc. 14-Nov-2019 14-Nov-2022 $608,247.31 $458,437.63
UPC CNN001 WSP Engineer of Record Services WSP USA, INC. 14-Nov-2019 14-Nov-2022 $68,808.69 $42,033.63
UPC CNN0001 Trackwork and Service Facility ALLAN MYERS VA, INC. 10-Dec-2020 03-Apr-2022 $12,850,298.51 $7,562,949.19
CSX Flagging and tie in construction CSX Transportation 29-Jun-2020 01-Jul-2022 $1,434,428.05 $585,678.14
AT&T design services AT&T Corp 13-Oct-2017 03-Jun-2023 $6,000.00 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.