Project Description
CitywideUpgrade traffic signal equipment to current technology. 
Project Manager
Randy Cooper
757.926.8702
rcooper@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
Less delay and fewer stops for the majority of drivers based on current volumes.

Relationship to Comprehensive Plan Themes
  • Sustainable
  • Accessible

Schedule

Activity Start Finish % Complete
PE/Design 02-Sep-2024 04-Jun-2027
70%
PE - Preliminary 02-Sep-2024 14-Feb-2025
100%
PE - Design 17-Feb-2025 04-Jun-2027
64%
PE - Environmental 17-Feb-2025 10-Apr-2026
100%
PE - Public Involvement 17-Feb-2025 10-Apr-2026
100%
Right of Way 01-Aug-2023 01-Aug-2023
100%
ROW - Land Acquisition 01-Aug-2023 01-Aug-2023
100%
ROW - Utility Relocation 01-Aug-2023 01-Aug-2023
100%
Construction 07-Jun-2027 27-Oct-2028
CA - Pre-Ad 07-Jun-2027 07-Jun-2027
CA - Advertisement 08-Jun-2027 08-Jun-2027
CA - Bid Date 09-Jun-2027 09-Jun-2027
CA - Construction Award 10-Jun-2027 24-Nov-2027
CA - CEI 25-Nov-2027 25-Nov-2027
CA - Construction 26-Nov-2027 26-Oct-2028
CA - Construction Closeout 27-Oct-2028 27-Oct-2028
Project Closeout 27-Oct-2028 27-Oct-2028
PE - Scoping 17-Feb-2025 10-Apr-2026
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.