Project Description
Project will install a mast arm traffic signal at the Rock Landing Drive and Omni Boulevard intersection with appropriate turn lanes.  Pedestrian pushbuttons, pedestrian signal displays, emergency vehicle preemption equipment, and video detection will be installed as part of the traffic signal.
Project Manager
Jennifer Butler
(757) 926-1582
butlerja@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
Improve safety at the intersection.

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 14-Jul-2020 29-Apr-2022
100%
PE - Preliminary 14-Jul-2020 31-Aug-2020
100%
PE - Design 01-Sep-2020 29-Apr-2022
100%
PE - Environmental 01-Sep-2020 17-Aug-2021
100%
PE - Public Involvement 01-Sep-2020 31-Dec-2021
100%
Right of Way 02-May-2022 01-Dec-2023
100%
ROW - Utility Easements and Utility Relocation 02-May-2022 01-Dec-2023
100%
Construction 30-May-2024 04-Jan-2027
75%
CA - Pre-Ad 04-Dec-2023 01-Mar-2024
100%
CA - Advertisement 30-May-2024 02-Jul-2024
100%
CA - Bid Date 02-Jul-2024 02-Jul-2024
100%
CA - Construction Award 03-Jul-2024 08-Aug-2024
100%
CA - CEI 22-Jul-2024 31-Aug-2026
85%
CA - Construction 02-Dec-2024 31-Aug-2026
82%
CA - Construction Closeout 01-Sep-2026 04-Jan-2027
Project Closeout 05-Jan-2027 21-Jun-2027
PE - Scoping 05-Aug-2021 05-Aug-2021
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
UPC 111065 Traffic Signal and Turn Lane Installation: Rock Landing Drive and Omni Boulevard - Design CLARK NEXSEN INC. 20-Nov-2020 17-Aug-2021 $94,892.00 $93,446.00
CEI Services ATCS, P.L.C 25-Jun-2024 28-Feb-2025 $147,787.81 $95,447.69
111065 Traffic Signal and Turn Lane - Basic Construction ALLAN MYERS VA, INC. 02-Dec-2024 15-Jun-2025 $2,360,292.40 $1,246,928.23
WR 10769652 UNDERGROUND RELOCATION VIRGINIA ELECTRIC AND POWER COMPANY 02-Apr-2025 30-Apr-2025 $45,952.81 $0.00
Light Pole Relocation VIRGINIA ELECTRIC AND POWER COMPANY 02-Apr-2025 07-Apr-2025 $2,489.33 $2,489.33
Vault Relocatioin COX COMMUNICATIONS INC. 04-Feb-2025 31-Mar-2025 $4,116.18 $0.00
Power to Traffic Signal VIRGINIA ELECTRIC AND POWER COMPANY 13-Mar-2026 13-Mar-2026 $8,221.55 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.