Project Description
Project will install a mast arm traffic signal at the Jefferson Avenue and Pavilion Place intersection.  Pedestrian pushbuttons, pedestrian signal displays, emergency vehicle preemption equipment, and video detection will be installed as part of the traffic signal. 
Project Manager
Jennifer Butler
(757) 926-1582
butlerja@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
Improve safety at the intersection.

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 14-Jul-2020 22-Jun-2023
100%
PE - Preliminary 14-Jul-2020 31-Aug-2020
100%
PE - Design 01-Sep-2020 22-Jun-2023
100%
PE - Environmental 01-Sep-2020 17-Aug-2021
100%
PE - Public Involvement 01-Sep-2020 31-Dec-2021
100%
Right of Way 23-Jun-2023 23-Jun-2023
100%
ROW - Utility Easements and Utility Relocation 23-Jun-2023 23-Jun-2023
100%
Construction 09-Jan-2023 25-Mar-2026
100%
CA - Pre-Ad 09-Jan-2023 13-Jun-2023
100%
CA - Advertisement 30-May-2024 02-Jul-2024
100%
CA - Bid Date 02-Jul-2024 02-Jul-2024
100%
CA - Construction Award 03-Jul-2024 08-Aug-2024
100%
CA - CEI 22-Jul-2024 19-Nov-2025
100%
CA - Construction 02-Dec-2024 19-Nov-2025
100%
CA - Construction Closeout 20-Nov-2025 25-Mar-2026
100%
Project Closeout 26-Mar-2026 09-Sep-2026
28%
PE - Scoping 05-Aug-2021 05-Aug-2021
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
UPC 111035 Traffic Signal Installation: Jefferson Avenue at Pavilion Place - Design Services CLARK NEXSEN INC. 20-Nov-2020 17-Aug-2021 $82,632.00 $77,638.00
CEI Services ATCS, P.L.C 25-Jun-2024 28-Feb-2025 $147,787.51 $72,367.89
111035 Traffic Signal - Basic Construction ALLAN MYERS VA, INC. 02-Dec-2024 15-Jun-2025 $1,232,037.00 $1,176,784.40

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.