Project Description
This construction Package will build the Station Bulding, Track platform and finish the Site.
Project Manager
Vincent Urbano
757.926.8694
vurbano@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
This project will provide a centralized multimodal transit facility for the City with important link

Relationship to Comprehensive Plan Themes
  • Accessible

Schedule

Activity Start Finish % Complete
PE/Design 15-Oct-2012 18-Jun-2017
100%
PE - Preliminary 15-Oct-2012 28-Nov-2012
100%
PE - Design 17-Dec-2012 18-Jun-2017
100%
PE - Environmental 13-Dec-2013 03-Feb-2016
100%
PE - Public Involvement 13-Dec-2013 03-Feb-2016
100%
Right of Way 19-Sep-2016 08-Jul-2018
100%
ROW - Land Acquisition 19-Sep-2016 07-Jun-2017
100%
ROW - Utility Relocation 15-Jan-2018 08-Jul-2018
100%
Construction 07-Feb-2020 25-Nov-2022
85%
CA - Pre-Ad 07-Feb-2020 25-Feb-2020
100%
CA - Advertisement 26-Feb-2020 01-Apr-2020
100%
CA - Bid Date 23-Apr-2020 23-Apr-2020
100%
CA - Construction Award 24-Apr-2020 17-Jun-2020
100%
CA - CEI 04-Jan-2021 28-May-2022
100%
CA - Construction 03-Jul-2021 26-Sep-2022
80%
CA - Construction Closeout 27-Sep-2022 25-Nov-2022
Project Closeout 26-Nov-2022 17-Dec-2022

Comments

Site grading underway for roads and parking areas. 06/20/2022

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
UPC 109076 Construction Inspections and Administration A. Morton Thomas & Associates Inc. 14-Nov-2019 14-Nov-2022 $895,388.55 $623,914.31
UPC 109076 Engineer of records Services WSP USA, INC. 14-Nov-2019 14-Nov-2022 $53,030.08 $43,064.25
UPC 109076 NNTC Station, Platform and Site Finishes MCKENZIE CONSTRUCTION CORPORATION 04-Jan-2021 29-Mar-2022 $13,928,335.08 $8,140,003.33
CSX Construction Agreement CSX Transportation 29-Jun-2020 01-Jul-2022 $385,209.49 $4,976.49

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.