Schedule

Activity Start Finish % Complete
PE/Design 15-Oct-2012 18-Jun-2017
100%
PE - Preliminary 15-Oct-2012 28-Nov-2012
100%
PE - Design 17-Dec-2012 18-Jun-2017
100%
PE - Environmental 13-Dec-2013 03-Feb-2016
100%
PE - Public Involvement 13-Dec-2013 03-Feb-2016
100%
Right of Way 19-Sep-2016 08-Jul-2018
100%
ROW - Land Acquisition 19-Sep-2016 07-Jun-2017
100%
ROW - Utility Relocation 15-Jan-2018 08-Jul-2018
100%
Construction 07-Feb-2020 31-Oct-2024
100%
CA - Pre-Ad 07-Feb-2020 25-Feb-2020
100%
CA - Advertisement 26-Feb-2020 01-Apr-2020
100%
CA - Bid Date 23-Apr-2020 23-Apr-2020
100%
CA - Construction Award 24-Apr-2020 17-Jun-2020
100%
CA - CEI 04-Jan-2021 10-Nov-2023
100%
CA - Construction 03-Jul-2021 30-Sep-2024
100%
CA - Construction Closeout 01-Oct-2024 31-Oct-2024
100%
Project Closeout 01-Nov-2024 01-Dec-2024
100%

Comments

Pond repairs to begin 3/25/26 03/23/2026

work plan being formulated for pond repairs. 03/16/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
UPC 109076 Construction Inspections and Administration A. Morton Thomas & Associates Inc. 14-Nov-2019 14-Nov-2022 $2,070,643.64 $2,068,727.06
UPC 109076 Engineer of records Services WSP USA, INC. 14-Nov-2019 14-Nov-2022 $90,155.52 $90,155.52
UPC 109076 NNTC Station, Platform and Site Finishes M B KAHN CONSTRUCTION CO INC 04-Jan-2021 29-Mar-2022 $14,553,439.15 $14,522,597.17
CSX Construction Agreement CSX Transportation 29-Jun-2020 01-Jul-2022 $469,543.78 $469,543.78
Dominion WR 10430575 Street lights VIRGINIA ELECTRIC AND POWER COMPANY 17-May-2022 30-May-2022 $6,656.23 $6,656.23
Dominion WR 10565491 and 10573969 Newport News - Engineering 13-Oct-2022 20-Oct-2022 $1,111.43 $1,058.38
Liquidated Damages Newport News - Engineering 01-Dec-2022 30-Dec-2022 $2,226,250.00 $0.00
COX FIBER SERVICE TO 500B BLAND BLVD (COX CIR: 175 Newport News - Engineering 01-Nov-2022 20-Dec-2022 $86,935.90 $86,935.90
Precision Mmeasurements Inc Plat work at NNTC Newport News - Engineering 10-Apr-2024 31-May-2024 $15,734.60 $7,867.30
Additional stripping Newport News - Engineering 24-Jul-2024 01-Aug-2024 $4,800.00 $4,800.00
city security cameras Newport News - Engineering 26-Aug-2024 28-Aug-2024 $32,730.66 $0.00
CIty ACS system Newport News - Engineering 07-Aug-2024 12-Aug-2024 $2,985.51 $0.00
12 parking lot signs modified for ADA Newport News - Engineering 16-Aug-2024 13-Sep-2024 $3,701.24 $3,701.24
Core drill SWM structure Newport News - Engineering 04-Oct-2024 31-Oct-2024 $6,331.23 $0.00
NNTC overflow structure rehab CENTENNIAL CONTRACTORS ENTERPRISES, INC 18-Sep-2025 15-Oct-2025 $9,006.50 $9,006.50
Conversion of bioretention area to swale and cored manhole CENTENNIAL CONTRACTORS ENTERPRISES, INC 02-Mar-2026 31-Mar-2026 $39,027.39 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.