Project Description
This construction Package will perform site grading and utility relocations.
Project Manager
Vincent Urbano
757.926.8694
vurbano@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
A centralized, multi-modal Amtrak facility w/access to airport, HRT, taxis, bus, light rail, etc.

Relationship to Comprehensive Plan Themes
  • Accessible

Schedule

Activity Start Finish % Complete
PE/Design 15-Oct-2012 29-May-2017
100%
PE - Preliminary 15-Oct-2012 28-Nov-2012
100%
PE - Design 17-Dec-2012 29-May-2017
100%
PE - Environmental 13-Dec-2013 03-Feb-2016
100%
PE - Public Involvement 13-Dec-2013 03-Feb-2016
100%
Right of Way 19-Sep-2016 08-Jul-2018
100%
ROW - Land Acquisition 19-Sep-2016 07-Jun-2017
100%
ROW - Utility Relocation 15-Jan-2018 08-Jul-2018
100%
Construction 01-May-2020 12-Nov-2021
100%
CA - Pre-Ad 01-May-2020 07-May-2020
100%
CA - Advertisement 08-May-2020 28-May-2020
100%
CA - Bid Date 28-May-2020 28-May-2020
100%
CA - Construction Award 29-May-2020 10-Jun-2020
100%
CA - CEI 29-Jun-2020 29-Apr-2021
100%
CA - Construction 29-Jun-2020 13-Sep-2021
100%
CA - Construction Closeout 14-Sep-2021 12-Nov-2021
100%
Project Closeout 13-Nov-2021 04-Dec-2021
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Construction Inspection and Administration Services A. Morton Thomas & Associates Inc. 14-Nov-2019 14-Nov-2022 $1,018,885.50 $1,018,885.50
UPC 109075 WSP Engineer of Record Services WSP USA, INC. 14-Nov-2019 14-Nov-2022 $28,161.23 $28,134.73
Inspection Services for HRSD work for UPC 109075 WHITMAN, REQUARDT AND ASSOC. LLP 04-Mar-2020 03-Dec-2020 $225,943.72 $225,943.72
UPC 109075 NNTC Grading, Drainage and Utilities BASIC CONSTRUCTION CO.,L.L.C 29-Jun-2020 29-Apr-2021 $8,209,927.01 $8,171,699.17
CSX Flagging CSX TRANSPORTATION INC 29-Jun-2020 02-Dec-2020 $378,053.21 $378,053.21

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.