Project Description
Convert existing span wire to a mast arm traffic signal at the intersection of Warwick Blvd and Harpersville Rd. The project will also include pedestrian countdown displays with push buttons, emergency vehicle preemption equipment, and a left turn lane.A complete modern traffic signal adds to the safety of the citizens by reducing crash potential as well as lowered maintenance costs.  The mast arm signal also adds to the aesthetic appeal of the City which can increase property values and increase business owner confidence while reducing congestion through more efficient traffic flow.
Project Manager
Melaney Hollins
757.926.8617
hollinsmn@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
Reduced crash potential and congestion, more efficient traffic flow, lower maintenance costs.

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 17-Aug-2016 15-Jan-2025
100%
PE - Preliminary 01-Mar-2018 19-Apr-2018
100%
PE - Design 20-Apr-2018 11-Dec-2024
100%
PE - Environmental 28-Mar-2017 30-Oct-2024
100%
PE - Public Involvement 12-Dec-2024 15-Jan-2025
100%
Right of Way 18-May-2021 15-Apr-2022
100%
ROW - Land Acquisition 18-May-2021 15-Apr-2022
100%
ROW - Utility Relocation 18-May-2021 15-Apr-2022
100%
Construction 03-Dec-2024 08-Oct-2027
44%
CA - Pre-Ad 03-Dec-2024 11-Mar-2025
100%
CA - Advertisement 12-Mar-2025 10-Apr-2025
100%
CA - Bid Date 11-Apr-2025 11-Apr-2025
100%
CA - Construction Award 14-Apr-2025 08-Aug-2025
100%
CA - CEI 08-Dec-2025 08-Oct-2027
14%
CA - Construction 09-Feb-2026 01-Jul-2027
6%
CA - Construction Closeout 02-Jul-2027 23-Sep-2027
Project Closeout 24-Sep-2027 16-Dec-2027
PE - Scoping 17-Aug-2016 22-Apr-2020
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
UPC #108794 Warwick Boulevard and Harpersville Road Intersection Improvements - Design Services MICHAEL BAKER INTERNATIONAL, INC 05-Apr-2018 31-Jan-2019 $108,187.67 $105,901.13
Install (3) streetlight on existing poles and remove (3) streetlights from median VIRGINIA ELECTRIC AND POWER COMPANY 31-Oct-2024 24-Oct-2024 $21,640.28 $21,640.28
CEI Services Volkert, Inc. 08-May-2025 20-Sep-2027 $153,498.60 $8,773.35
Construction of UPC 108794 Warwick Blvd and Harpersville Rd Intersection Improvements BRYANT-RITTER HEWITT ELECTRIC CORP 01-Mar-2026 17-Jun-2027 $1,138,125.73 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.