Project Description
Location:  Intersection of Briarfield Rd and Marshall AveProject:  Convert existing span wire traffic signal to a mast arm traffic signal at the intersection of Briarfield Rd and Marshall Ave.Perfomance/Outcome:  A complete modern traffic signal adds to the safety of the citizens by reducing crash potential as well as lowered maintenance costs. The mast arm signal also adds to the aesthetic appeal of the City which can increase property values and increase business owner confidence while reducing congestion through more efficient traffic flow.
Project Manager
Ioana Verde
757.926.8690
braswelld@nnva.gov
Inspector
Larry Brown
757.933.2318
lbrown@jmt.com

How does this project serve Newport News’ citizens?
A complete modern traffic signal adds to the safety of the citizens by reducing crash potential as w

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 26-Apr-2019 03-May-2024
100%
PE - Preliminary 26-Apr-2019 19-Jul-2019
100%
PE - Design 22-Jul-2019 03-May-2024
100%
PE - Environmental 15-Apr-2019 15-Apr-2019
100%
PE - Public Involvement 01-Dec-2023 01-Dec-2023
100%
Right of Way 12-Jun-2017 03-May-2024
100%
ROW - Land Acquisition 12-Jun-2017 03-May-2024
100%
ROW - Utility Relocation 03-Jul-2017 31-Aug-2018
100%
Construction 17-May-2024 21-Dec-2026
80%
CA - Pre-Ad 17-May-2024 11-Sep-2024
100%
CA - Advertisement 12-Sep-2024 10-Oct-2024
100%
CA - Bid Date 11-Oct-2024 11-Oct-2024
100%
CA - Construction Award 14-Oct-2024 01-Apr-2025
100%
CA - CEI 02-Apr-2025 30-Nov-2026
72%
CA - Construction 02-Apr-2025 17-Nov-2026
74%
CA - Construction Closeout 18-Nov-2026 21-Dec-2026
Project Closeout 22-Dec-2026 19-Feb-2027

Comments

Signal pole foundation on the fire station corner poured on 3/20. Waiting on Dominion to finalize the WR/design/proposal to deenergize the lines to allow the remaining signal pole foundation to be poured. 03/20/2026

Fire hydrant relocation completed 3/11/2026 03/11/2026

On-site meetings with the contractor, CEI consultant and Dominion power on 2/06/26 and 2/18/26 02/02/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Traffic Signal and Pedestrian Improvements at Briarfield Road and Marshall Avenue Design Johnson, Mirmiran & Thompson, Inc. 07-Apr-2016 20-Mar-2019 $0.00 $0.00
Design Revision for Traffic Signal and Pedestrian Improvements at Briarfield Road and Marshall Avenu Johnson, Mirmiran & Thompson, Inc. 22-Jul-2019 18-Mar-2020 $8,091.12 $8,091.12
Design Revision - Traffic Signal and Ped Improvements at Briarfield and Marshall - Ped poles Johnson, Mirmiran & Thompson, Inc. 21-Feb-2022 16-Mar-2022 $6,556.40 $6,556.40
Design Revision-Traffic Signal and Pedestrian Improvements and Briarfield and Marshall Johnson, Mirmiran & Thompson, Inc. 12-Jun-2023 11-Aug-2023 $3,971.54 $3,971.54
Bidding and Construction Administration Services for Briarfield and Marshall Signal Improvements Johnson, Mirmiran & Thompson, Inc. 01-Nov-2024 15-Apr-2026 $56,603.20 $28,096.30
Traffic Signal and Pedestrian Improvements at Briarfield Road and Marshall Avenue BRYANT-RITTER HEWITT ELECTRIC CORP 01-Apr-2025 01-Apr-2026 $1,019,796.25 $389,454.73

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.