Project Description
Project Manager
Aaron Deneb
757-926-8001
adeneb@nnva.gov
Inspector
Deneb

How does this project serve Newport News’ citizens?
Lighting for this location to meet standards will maintain visible and safe conditions for pedestria

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Healthy & Safe
  • Balances Good Places & New Spaces

Schedule

Activity Start Finish % Complete
PE/Design 06-Nov-2017 29-Sep-2023
100%
PE - Preliminary 06-Nov-2017 27-Aug-2018
100%
PE - Design 28-Aug-2018 29-Sep-2023
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 02-Oct-2023 07-Oct-2027
67%
CA - Construction 02-Oct-2023 30-Sep-2027
67%
CA - Construction Closeout 01-Oct-2027 07-Oct-2027
Project Closeout 22-Jun-2020 26-Dec-2025
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
This project installs 19 new Cobra Head LED fixtures and poles for the first phase of this developme VIRGINIA ELECTRIC AND POWER COMPANY 25-Mar-2019 20-Nov-2019 $110,358.57 $110,358.57
Project to Install 65 LED Colonial fixtures on 18' fiberglass poles VIRGINIA ELECTRIC AND POWER COMPANY 15-Aug-2019 28-Feb-2020 $104,257.56 $104,257.56
Huntington Pointe Phase 1B3 VIRGINIA ELECTRIC AND POWER COMPANY 03-Feb-2023 29-Mar-2023 $202,169.58 $202,169.58
Dominion Energy to Install (29) new colonial cutoff fixtures to the area of upper Stafford Lane VIRGINIA ELECTRIC AND POWER COMPANY 03-Nov-2023 31-Jan-2024 $77,402.88 $77,402.88

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.