Project Description
Location:  River Road from Raleigh Road to Randolph Road / Burns Avenue.Scope:  The Raleigh Road and River Road Drainage Improvements includes study, analysis and improvements of the existing drainage system. The project includes surveying and analyzing of the existing drainage system to determine its deficiencies and propose plans for enhancing and improving the system. The project goals are to increase the capacity of the existing system to a level that it can handle the area’s runoff volume during the major storm events.Performance/Outcome:  Project benefits are reduction in risk of flooding and damages to few properties along Raleigh Road; and enhance the capacity of the existing drainage system.
Project Manager
Hai Tran
757.926.8264
htran@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
Project benefits are reduction in risk of flooding and damages to few properties along Raleigh Road;

Relationship to Comprehensive Plan Themes
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 12-Sep-2022 22-Jan-2026
100%
PE - Preliminary 12-Sep-2022 28-Nov-2022
100%
PE - Design 29-Nov-2022 22-Jan-2026
100%
Construction 23-Jan-2026 07-Jan-2027
48%
CA - Pre-Ad 23-Jan-2026 30-Jan-2026
100%
CA - Advertisement 02-Feb-2026 26-Feb-2026
100%
CA - Bid Date 27-Feb-2026 27-Feb-2026
100%
CA - Construction Award 02-Mar-2026 29-Apr-2026
100%
CA - CEI 30-Apr-2026 30-Apr-2026
100%
CA - Construction 01-May-2026 05-Nov-2026
38%
CA - Construction Closeout 06-Nov-2026 07-Jan-2027
Project Closeout 08-Jan-2027 17-Feb-2027

Comments

TUCI will start on July 14. Changed order (changes of structuress sizes) is in proccess. 07/10/2026

TUCI will start part of mobilization week of June 8. Real work will start at end of June, once all RFIs and Submittal being squared away. 06/05/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Raleigh Road Drainage Improvements: Develop a design and construction plan to alleviate flooding on Johnson, Mirmiran & Thompson, Inc. 26-Jan-2023 31-Dec-2024 $149,909.50 $140,484.53
Raleigh Road Drainage Improvements - Construction TIDEWATER UTILITY CONSTRUCTION 01-Jun-2026 29-Oct-2026 $1,422,875.01 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.