Project Description
Pump Station 043 was constructed in 1964 and serves a trailer park, two multi-story apartment complexes, a residential area, and a large shopping center.  The pump station has insufficient capacity to meet peak flows and relies on a temporary emergency bypass pump to meet flows during storm events.  The generator room, a later addition to the building, is settling and separating from the original building.  This project will provide new correctly sized pumps, modify and repair the building, install a new standby diesel-driven pump in case of power failures, replace electrical and control equipment and ventilation fans, and provide odor control. Scope of Work:- Demolition of existing generator room including base slab, and portions of existing driveway.- Removal of the existing pumps and motors, suction & discharge piping, associated valves, and existing standby emergency generator. - Removal of existing electrical equipment, instrumentation and control panels. - Removal of existing force main, installation of new 6-inch and 8-inch force main pipe, and installation of new emergency bypass piping.- Site restoration.- New control room wall and repair of existing roof. - Installation of new flow meter vault and flow meter. - Installation of two (2) vertical close-coupled solid handling pumps and one (1) diesel-driven self-priming pump. - New supply and exhaust ventilators and electric heaters. - Wet well Rehab.- New instrumentation & controls. 
Project Manager
Landon Kee
757-926-8668
keeld@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 12-May-2020 29-Dec-2023
100%
PE - Preliminary 12-May-2020 06-May-2021
100%
PE - Design 25-Jan-2022 29-Dec-2023
100%
Construction 01-Jan-2024 18-Nov-2025
100%
CA - Pre-Ad 01-Jan-2024 06-Mar-2024
100%
CA - Advertisement 07-Mar-2024 04-Apr-2024
100%
CA - Bid Date 04-Apr-2024 04-Apr-2024
100%
CA - Construction Award 05-Apr-2024 17-Apr-2024
100%
CA - CEI 18-Apr-2024 09-Aug-2024
100%
CA - Construction 12-Sep-2024 11-Nov-2025
100%
CA - Construction Closeout 12-Nov-2025 18-Nov-2025
100%
Project Closeout 19-Nov-2025 25-Nov-2025
100%

Comments

A notice proceed was issued for 9/12/24, with a completion date of on or before 11/11/25. The contractor was on site 7/25/25 installing the new ship ladder in the dry well. Their electricians were also on site continuing to work on electrical conduit and equipment. 09/12/2024

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Professional Engineering Services - PS 043 Rehab (PER phase) WHITMAN, REQUARDT AND ASSOC. LLP 12-May-2020 01-Sep-2020 $149,580.00 $133,037.01
PUMP STATION 043 REHABILITATION (Professional Design Services) WHITMAN, REQUARDT AND ASSOC. LLP 25-Jan-2022 20-Sep-2022 $173,800.00 $173,800.00
PUMP STATION 043 Force Main REHABILITATION (Professional Design Services) WHITMAN, REQUARDT AND ASSOC. LLP 25-Jan-2022 20-Sep-2022 $207,513.28 $180,140.94
Pump Station No. 043 Rehabilitation SHAW CONSTRUCTION, CORP 12-Sep-2024 11-Nov-2025 $2,593,350.95 $2,364,598.32
CA & CI Services - Pump Station 043 Rehab WHITMAN, REQUARDT AND ASSOC. LLP 05-Aug-2024 29-Jan-2026 $67,527.00 $60,691.67

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.