Project Description
Location: Oak Ave between 18th St and 16th St.  Project: Replace the deteriorating sanitary sewer trunk main and abandon existing sidewalk sewers, along Oak Ave. NOTE: THE DESIGN PORTION OF 20TH ST SANITARY SEWER PROJECT IS COMBINED UNDER THE PURCHASE ORDER FOR OAK AVE SANITARY SEWER PROJECT. Performance/Outcome: Reduces infiltration/intrusion in sanitary sewers and reduces O & M cost; improves water quality
Project Manager
Laura Harrell
757.926.8336
harrelllj@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
Reduce I&I in Sanitary Sewers and Reduce Operations and Maintenance costs. Improve water quality.

Relationship to Comprehensive Plan Themes
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 02-Nov-2018 27-Feb-2026
100%
PE - Preliminary 02-Nov-2018 02-Nov-2018
100%
PE - Design 05-Nov-2018 27-Feb-2026
100%
Construction 01-Jul-2026 05-Nov-2027
CA - Pre-Ad 01-Jul-2026 11-Aug-2026
CA - Advertisement 12-Aug-2026 22-Sep-2026
CA - Bid Date 23-Sep-2026 23-Sep-2026
CA - Construction Award 15-Oct-2026 28-Oct-2026
CA - CEI 08-Feb-2021 08-Feb-2021
100%
CA - Construction 28-Oct-2026 01-Nov-2027
CA - Construction Closeout 01-Nov-2027 05-Nov-2027
Project Closeout 05-Nov-2027 02-Dec-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Oak Ave Section III (CA Services) Johnson, Mirmiran & Thompson, Inc. 21-Oct-2025 31-May-2027 $19,000.00 $5,950.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.