Project Description
Location:  Nicewood AreaProject:  Alleviate flooding at the intersection of Malden Lane and Maryle Court during significant rain events. A recent storm sewer model identifies that the existing system is inadequate and confirms that flooding occurs.Performance/Outcome:  Reduce risk of flooding and damages; the new drainage systems will be designed to meet present Stormwater Management Standards. Approximately 70 homes and approximately 2200 LF of roadway will benefit from the installation of the stormwater drainage system.
Project Manager
Hai Tran
757.926.8264
tranhn@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
The benefits of these phases of the project are reduction in risk of flooding and damages, and the n

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 14-Nov-2022 31-Dec-2026
84%
PE - Preliminary 23-Oct-2023 23-Oct-2023
100%
PE - Design 14-Nov-2022 31-Dec-2026
84%
PE - Environmental 22-Feb-2023 21-Jun-2023
100%
PE - Public Involvement 06-Sep-2024 06-Sep-2024
100%
Right of Way 01-Apr-2026 30-Nov-2026
17%
ROW - Land Acquisition 01-Apr-2026 30-Nov-2026
17%
ROW - Utility Relocation 01-Jul-2026 27-Sep-2026
Construction 01-Jan-2027 13-Dec-2027
CA - Pre-Ad 01-Jan-2027 10-Jan-2027
CA - Advertisement 11-Jan-2027 09-Feb-2027
CA - Bid Date 10-Feb-2027 10-Feb-2027
CA - Construction Award 11-Feb-2027 27-Mar-2027
CA - CEI 28-Mar-2027 28-Mar-2027
CA - Construction 29-Mar-2027 14-Oct-2027
CA - Construction Closeout 15-Oct-2027 13-Dec-2027
Project Closeout 14-Dec-2027 12-Jan-2028

Comments

City received revised Plats from Jacob. Waterworks has provided comments on the 60% design. 05/08/2026

Jacob will revise the Plats per comments from City. 04/24/2026

Jacob submitted the revised Plats and the 60% Cost Estimate. They are under review. 04/10/2026

Jacob submitted 60% design (3/6/25). It is under review. The survey plats are forthcoming. 03/06/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Nicewood Area Drainage Improvements Design JACOBS ENGINEERING GROUP, INC 26-Jan-2023 30-Jun-2024 $324,884.06 $268,757.43

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.