Project Description
Improvements to the dam for Mariners' Lake include the armoring of the entire downstream embankment, rehabilitation of the outfall culvert, and construction of a low level inlet structure to control the lake level and discharge from the lake. These improvements are necessary in order for the dam to receive certification of operation and maintenance from the State Department of Conservation and Recreation (DCR), Dam Safety Division.  The present spillway operation has stop-logs that are removed or replaced by Mariners' Museum staff using a crane machine to lift and place the logs. The dam has been overtopped by large storm events which have caused minor damage to the area that have been repaired.  In addition to these improvements, off-shore stabilization will be performed prior to removal of shoreline vegetation based on DCR's requirements.
Project Manager
Hai Tran
tranhn@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
Facility will pass the required storm event which is the 1/2 Probable Maximum Flood

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Healthy & Safe
  • Respects its Uniqueness

Schedule

Activity Start Finish % Complete
PE/Design 05-Aug-2013 26-May-2023
100%
PE - Preliminary 05-Aug-2013 28-Aug-2020
100%
PE - Design 31-Aug-2020 26-May-2023
100%
PE - Environmental 07-Jun-2021 01-Apr-2022
100%
PE - Public Involvement 20-Sep-2021 29-Oct-2021
100%
Construction 29-May-2023 30-May-2025
63%
CA - Pre-Ad 29-May-2023 22-Jun-2023
100%
CA - Advertisement 23-Jun-2023 14-Aug-2023
100%
CA - Bid Date 15-Aug-2023 15-Aug-2023
100%
CA - Construction Award 16-Aug-2023 29-Dec-2023
100%
CA - CEI 01-Jan-2024 05-Jan-2024
100%
CA - Construction 08-Dec-2023 07-Apr-2025
56%
CA - Construction Closeout 08-Apr-2025 30-May-2025
Project Closeout 02-Jun-2025 30-Jul-2025

Comments

Construction Progress as of August 30, 2024: • The construction is in Phase 4 – Traffic is opened. • Continue to work on Sluice Gate replacements. First slice gate was installed. • Continued installing soil stabilization measures along with seeding and site prepping. • Prep for Wetland Planting 09/03/2024

Construction Progress as of August 23, 2024: • The construction is in Phase 4 – Traffic is opened. • Demoed top slab and started repairing sluice gates • Installed wetland planting mix • Installed remaining granite curb. Restored median • Worked on slope protection. 08/23/2024

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Lake Maury Improvements (design) Arcadis-U.s., INC. 30-May-2011 30-Jun-2011 $141,800.00 $141,800.00
Lake Maury Spillway Improvements (design) Arcadis-U.s., INC. 10-Oct-2013 30-Jun-2019 $227,088.75 $227,088.75
Lake Maury Spillway Improvements - Additional Services (design) Arcadis-U.s., INC. 02-Feb-2016 31-Mar-2019 $89,252.60 $89,252.60
Lake Maury Spillway Improvements - Additional Services (design1) Arcadis-U.s., INC. 01-May-2017 31-Mar-2019 $99,635.00 $99,635.00
Task #5: Conditional Certification Application & Reallocated Design Fees Arcadis-U.s., INC. 09-Apr-2020 31-Jul-2020 $328,500.00 $328,500.00
Lions Bridge Dam Task #6 - Final Design Arcadis-U.s., INC. 25-Jan-2021 30-Apr-2022 $459,383.00 $459,383.00
Dominion Energy Pole Removal and Reinstallation VIRGINIA ELECTRIC AND POWER COMPANY 28-Apr-2022 31-Dec-2022 $13,300.05 $13,300.05
Task #7-Lions Bridge Dam Construction & Inspection Services Arcadis-U.s., INC. 08-Aug-2022 31-Mar-2025 $386,186.89 $229,698.59
Lions Bridge Dam Improvements - Construction CORMAN KOKOSING CONSTRUCTION COMPANY 08-Jan-2024 07-Jan-2025 $7,584,108.75 $6,261,141.20

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.