Project Description
Location:  From the intersection of Marrow Drive and Huxley Place to Lynn Dr. It is in the Glendale subdivision.The purpose of this project is to repair and/or replace approximately 2,500 LF of deteriorating stormwater pipes which includes, reinforced concrete pipes (RCP) and corrugated metal pipes (CMP) in the Huxley Place/Glendale Subdivision. The project also needs to provide any additional necessary drainage improvements. This storm drainage system provides drainage for more than 100 homes, and further deterioration/broken stormwater pipes could lead to sinkholes and depressions causing risk to structures, roads, and public safety.  Any old existing corrugated metal storm pipes will be replaced with RCP, which has a longer life expectancy.  Perfomance/Outcome:  Alleviate flooding and ease citizen flooding concerns.
Project Manager
Khanh Khuu
757-926-8656
khuukx@nnva.gov
Inspector
Not yet assigned

How does this project serve Newport News’ citizens?
To alleviate known flooding issues and replace failing stormwater infrastructure of high importance

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe
  • Respects its Uniqueness

Schedule

Activity Start Finish % Complete
PE - Preliminary 08-Aug-2022 14-Nov-2022
100%
PE - Design 15-Nov-2022 09-Sep-2024
100%
PE - Environmental 26-Mar-2020 26-Mar-2020
100%
Construction 03-Mar-2025 10-Dec-2026
67%
CA - Pre-Ad 03-Mar-2025 12-Mar-2025
100%
CA - Advertisement 13-Mar-2025 07-Apr-2025
100%
CA - Bid Date 08-Apr-2025 08-Apr-2025
100%
CA - Construction Award 09-Apr-2025 23-May-2025
100%
CA - CEI 24-May-2025 24-May-2025
100%
CA - Construction 28-Jul-2025 11-Sep-2026
70%
CA - Construction Closeout 12-Sep-2026 10-Dec-2026
Project Closeout 11-Dec-2026 10-Mar-2027

Comments

5/8 - A substantial completion walk-through has been conducted this week. There were several items on the punch list that required correction. 05/08/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Huxley Place Drainage Improvements JACOBS ENGINEERING GROUP, INC 20-Dec-2022 30-Sep-2024 $208,528.40 $177,106.65
Dominion Energy to locate 2 existing lift poles within ROW on Huxley Place VIRGINIA ELECTRIC AND POWER COMPANY 24-Oct-2023 01-Sep-2024 $1,672.06 $0.00
Huxley Place CIPP Lining TRI-STATE UTILITIES CO 08-Apr-2025 31-Jul-2025 $734,532.82 $734,532.82
Huxley Place Drainage Improvements HENRY S BRANSCOME LLC 28-Jul-2025 11-Sep-2026 $2,147,004.00 $1,964,617.10
Huxley Place Drainage Improvements - Construction Administration Services CENTURY ENGINEERING, INC 15-Dec-2025 01-Sep-2026 $113,093.20 $45,173.89
Holding two lift poles (N0027 HK65 & HK81) for pipe installation on Huxley Place VIRGINIA ELECTRIC AND POWER COMPANY 08-Jan-2026 30-Jan-2026 $2,519.97 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.