Project Description
Location: Drainage system at Warwick Blvd and Edgemoor Dr. Project: The drainage system in Chelsea Place apartments drains to a channel along the CSX right-of-way, then through a small culvert to a drainage channel along Warwick Blvd.  The culvert under the railroad right-of-way is undersized and causes flooding in the parking lot of the apartments.  This project includes an analysis of the system with design and construction to improve drainage. Performance/Outcome: Alleviate flooding for the apartment parking lots and two apartment buildings housing 15 apartments.  Improve drainage upstream and downstream of the improvements by increasing flow through the drainage outfall of the apartments and diverting some of the flow from Edgemoor Drive to a new outfall.
Project Manager
Juan Carlos Morgado Jofre
757.926.8601
morgadojofrej@nnva.gov
Inspector

How does this project serve Newport News’ citizens?
Alleviate flooding for the apartment parking lots and two apartment buildings housing 15 apartments.

Relationship to Comprehensive Plan Themes
  • Sustainable
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 03-Sep-2012 01-Aug-2024
100%
PE - Preliminary 03-Sep-2012 05-Jan-2015
100%
PE - Design 06-Jan-2015 27-Jun-2020
100%
PE - Environmental 20-Feb-2015 19-Jul-2015
100%
PE - Public Involvement 01-Aug-2024 01-Aug-2024
100%
Right of Way 03-Jan-2018 01-Aug-2024
100%
ROW - Land Acquisition/Easement 03-Jan-2018 16-Sep-2022
100%
ROW - Utility Relocation 01-Aug-2024 01-Aug-2024
100%
Construction 18-Aug-2025 30-Aug-2026
71%
CA - Pre-Ad 18-Aug-2025 21-Aug-2025
100%
CA - Advertisement 22-Aug-2025 08-Sep-2025
100%
CA - Bid Date 09-Sep-2025 09-Sep-2025
100%
CA - Construction Award 10-Sep-2025 24-Oct-2025
100%
CA - CEI 25-Oct-2025 25-Oct-2025
100%
CA - Construction 26-Oct-2025 01-Jul-2026
80%
CA - Construction Closeout 02-Jul-2026 30-Aug-2026
Project Closeout 31-Aug-2026 29-Oct-2026

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
2021 Chelsea Place Storm Water Drainage Imp. Modify Design Documents and Update Scope of Sevices CORNWELL ENGINEERING GROUP 07-Apr-2021 31-Dec-2022 $67,130.00 $60,467.50
CSX Upload Doc Fees CSX TRANSPORTATION INC 24-Jan-2025 27-Jan-2025 $20,500.00 $12,483.08
SOIL BORING TEST AND REPORT AT CSX REQUEST GEOTECHNICAL ENVIRONMENTAL AND TESTING 19-May-2025 30-Jun-2026 $14,380.86 $14,380.86
Chelsea Place Howard Brothers Inc HOWARD BROTHERS CONTRACTOR, INC. 03-Nov-2025 13-Jul-2026 $2,522,327.04 $1,121,835.09
NXL - Construction Administration Services CENTURY ENGINEERING, INC 11-Dec-2025 01-Oct-2026 $123,727.96 $36,714.27

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.