Project Description
Project Manager
Thomas Cheney
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-May-2025 25-Jul-2025
100%
PE - Preliminary 01-May-2025 21-Jul-2025
100%
PE - Design 22-Jul-2025 22-Jul-2025
100%
PE - Environmental 23-Jul-2025 23-Jul-2025
100%
PE - Scoping 24-Jul-2025 24-Jul-2025
100%
PE - Public Involvement 25-Jul-2025 25-Jul-2025
100%
Right of Way 26-Jul-2025 27-Jul-2025
100%
ROW - Land Acquisition 26-Jul-2025 26-Jul-2025
100%
ROW - Utility Relocation 27-Jul-2025 27-Jul-2025
100%
Construction 28-Jul-2025 01-Jul-2026
100%
CA - Pre-Ad 28-Jul-2025 28-Jul-2025
100%
CA - Advertisement 29-Jul-2025 29-Jul-2025
100%
CA - Bid Date 30-Jul-2025 30-Jul-2025
100%
CA - Construction Award 31-Jul-2025 31-Jul-2025
100%
CA - CEI 01-Aug-2025 01-Aug-2025
100%
CA - Construction 01-Aug-2025 30-Jun-2026
100%
CA - Construction Closeout 01-Jul-2026 01-Jul-2026
100%
Project Closeout 02-Jul-2026 02-Jul-2026
100%
PE/Design 01-May-2025 05-May-2025
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Pavement Marking Plans ATCS, P.L.C 02-Jul-2025 01-Mar-2026 $17,892.98 $15,209.04
23rd Street Median BRANSCOME, INC 25-Jul-2025 31-Oct-2025 $115,303.57 $115,303.57
2026 Annual Citywide Resurfacing and Concrete Repairs West BRANSCOME, INC 18-Aug-2025 30-Jun-2026 $4,132,235.28 $2,517,677.10

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.