Project Description
Project Manager
Thomas Cheney
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-May-2025 05-May-2025
100%
PE - Preliminary 01-May-2025 01-May-2025
100%
PE - Design 02-May-2025 02-May-2025
100%
PE - Environmental 03-May-2025 03-May-2025
100%
PE - Scoping 04-May-2025 04-May-2025
100%
PE - Public Involvement 05-May-2025 05-May-2025
100%
Right of Way 06-May-2025 07-May-2025
100%
ROW - Land Acquisition 06-May-2025 06-May-2025
100%
ROW - Utility Relocation 07-May-2025 07-May-2025
100%
Construction 08-May-2025 01-Jul-2026
100%
CA - Pre-Ad 08-May-2025 08-May-2025
100%
CA - Advertisement 09-May-2025 09-May-2025
100%
CA - Bid Date 10-May-2025 10-May-2025
100%
CA - Construction Award 11-May-2025 11-May-2025
100%
CA - CEI 12-May-2025 12-May-2025
100%
CA - Construction 31-Jul-2025 30-Jun-2026
100%
CA - Construction Closeout 01-Jul-2026 01-Jul-2026
100%
Project Closeout 02-Jul-2026 02-Jul-2026
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Pavement Marking Plans ATCS, P.L.C 01-Jul-2025 01-Mar-2026 $127,335.03 $127,335.03
2026 Annual Citywide Resurfacing and Concrete Repairs East ALLAN MYERS VA, INC. 10-Oct-2025 30-Jun-2026 $8,237,760.84 $4,608,396.19
Striping Plans Jefferson Ave from Fort Eustis Blvd to Industrial Park Dr - ATCS ATCS, P.L.C 01-May-2026 15-May-2026 $14,625.59 $12,431.29

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.