Project Description
restrooms renovation
Project Manager
Bruce Wobser
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 31-Jan-2025 03-Oct-2025
100%
PE - Preliminary 31-Jan-2025 02-Feb-2025
100%
PE - Design 03-Feb-2025 30-Sep-2025
100%
PE - Environmental 01-Oct-2025 01-Oct-2025
100%
PE - Scoping 02-Oct-2025 02-Oct-2025
100%
PE - Public Involvement 03-Oct-2025 03-Oct-2025
100%
Right of Way 04-Oct-2025 14-Nov-2025
100%
ROW - Land Acquisition 04-Oct-2025 04-Oct-2025
100%
ROW - Utility Relocation 05-Oct-2025 14-Nov-2025
100%
Construction 15-Nov-2025 13-Jan-2027
56%
CA - Pre-Ad 15-Nov-2025 01-Jul-2026
100%
CA - Advertisement 02-Jul-2026 31-Jul-2026
37%
CA - Bid Date 01-Aug-2026 01-Aug-2026
CA - Construction Award 02-Aug-2026 31-Aug-2026
CA - CEI 01-Sep-2026 01-Sep-2026
CA - Construction 01-Sep-2026 29-Nov-2026
CA - Construction Closeout 30-Nov-2026 13-Jan-2027
Project Closeout 14-Jan-2027 13-May-2027

Comments

Parks requested a delay start until the end of the summer. 01/26/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
HUNTINGTON BEACH RESTROOM RENOVATION MCPHERSON DESIGN GROUP, PC 01-May-2025 16-May-2025 $3,162.05 $3,162.05

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.