Project Description
new restroom structure
Project Manager
Bruce Wobser
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 22-Jan-2025 03-Oct-2025
100%
PE - Preliminary 22-Jan-2025 27-Feb-2025
100%
PE - Design 28-Feb-2025 30-Sep-2025
100%
PE - Environmental 01-Oct-2025 01-Oct-2025
100%
PE - Scoping 02-Oct-2025 02-Oct-2025
100%
PE - Public Involvement 03-Oct-2025 03-Oct-2025
100%
Right of Way 04-Oct-2025 14-Nov-2025
100%
ROW - Land Acquisition 04-Oct-2025 04-Oct-2025
100%
ROW - Utility Relocation 05-Oct-2025 14-Nov-2025
100%
Construction 15-Nov-2025 03-May-2027
27%
CA - Pre-Ad 15-Nov-2025 01-Jul-2026
64%
CA - Advertisement 02-Jul-2026 31-Jul-2026
CA - Bid Date 01-Aug-2026 01-Aug-2026
CA - Construction Award 02-Aug-2026 31-Aug-2026
CA - CEI 01-Sep-2026 01-Sep-2026
CA - Construction 01-Sep-2026 19-Mar-2027
CA - Construction Closeout 20-Mar-2027 03-May-2027
Project Closeout 04-May-2027 31-Aug-2027

Comments

Parks requested a delay start until after summer. 01/23/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.