Project Description
Project Manager
Randy Cooper
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Feb-2024 17-Jan-2026
100%
PE - Preliminary 01-Feb-2024 01-Jul-2025
100%
PE - Design 02-Jul-2025 17-Jan-2026
100%
PE - Environmental 02-Jul-2025 28-Nov-2025
100%
PE - Scoping 02-Jul-2025 28-Nov-2025
100%
PE - Public Involvement 02-Jul-2025 28-Nov-2025
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 18-Jan-2026 01-Jan-2027
42%
CA - Pre-Ad 18-Jan-2026 01-Feb-2026
100%
CA - Advertisement 02-Feb-2026 02-Feb-2026
100%
CA - Bid Date 03-Feb-2026 03-Feb-2026
100%
CA - Construction Award 04-Feb-2026 04-Feb-2026
100%
CA - CEI 05-Feb-2026 05-Feb-2026
100%
CA - Construction 05-Feb-2026 31-Dec-2026
39%
CA - Construction Closeout 01-Jan-2027 01-Jan-2027
Project Closeout 02-Jan-2027 02-Jan-2027

Comments

All equipment has been ordered and delivered. Newport News Traffic Signal Shop is working on installation of equipment at 28 intersections. 04/13/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
HREL UPC 126624 Gridsmart Video Detetion CUBIC ITS INC 18-Dec-2025 20-Feb-2026 $621,034.00 $621,034.00
HREL UPC 126624 Gridsmart Video Detetion CUBIC ITS INC 23-Feb-2026 20-Mar-2026 $48,925.00 $48,925.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.