Project Description
Project Manager
Randy Cooper
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Feb-2024 27-Apr-2026
98%
PE - Preliminary 01-Feb-2024 01-Jul-2025
100%
PE - Design 02-Jul-2025 27-Apr-2026
94%
PE - Environmental 02-Jul-2025 08-Mar-2026
100%
PE - Scoping 02-Jul-2025 08-Mar-2026
100%
PE - Public Involvement 02-Jul-2025 08-Mar-2026
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 28-Apr-2026 20-Dec-2027
CA - Pre-Ad 28-Apr-2026 26-Jun-2026
CA - Advertisement 27-Jun-2026 25-Aug-2026
CA - Bid Date 26-Aug-2026 26-Aug-2026
CA - Construction Award 27-Aug-2026 24-Dec-2026
CA - CEI 25-Dec-2026 25-Dec-2026
CA - Construction 25-Dec-2026 19-Dec-2027
CA - Construction Closeout 20-Dec-2027 20-Dec-2027
Project Closeout 21-Dec-2027 21-Dec-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
123926 CCTV Equipment Newport News - Engineering 10-Mar-2026 23-Oct-2026 $37,991.64 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.