Project Description
Project Manager
Bruce Wobser
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 02-Apr-2025 02-Apr-2025
100%
PE - Preliminary 01-Jan-2025 01-Apr-2025
100%
PE - Design 02-Apr-2025 02-Apr-2025
100%
PE - Environmental 03-Apr-2025 03-Apr-2025
100%
PE - Scoping 04-Apr-2025 04-Apr-2025
100%
PE - Public Involvement 05-Apr-2025 05-Apr-2025
100%
Right of Way 06-Apr-2025 07-Apr-2025
100%
ROW - Land Acquisition 06-Apr-2025 06-Apr-2025
100%
ROW - Utility Relocation 07-Apr-2025 07-Apr-2025
100%
Construction 08-Apr-2025 13-Apr-2026
91%
CA - Pre-Ad 08-Apr-2025 21-Apr-2025
100%
CA - Advertisement 06-May-2025 16-Jun-2025
100%
CA - Bid Date 17-Jun-2025 17-Jun-2025
100%
CA - Construction Award 18-Jun-2025 17-Jul-2025
100%
CA - CEI 18-Jul-2025 18-Jul-2025
100%
CA - Construction 18-Jul-2025 27-Feb-2026
100%
CA - Construction Closeout 28-Feb-2026 13-Apr-2026
31%
Project Closeout 14-Apr-2026 12-Jun-2026

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Glazing of Historic Endview and Lee Hall Mansion CENTENNIAL CONTRACTORS ENTERPRISES, INC 01-Aug-2025 31-Aug-2025 $67,528.00 $67,528.00
Painting of Historic Endview and Lee Hall Mansion Frank Contracting, LLC 18-Aug-2025 15-Nov-2025 $116,500.00 $116,500.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.