Project Description
Provide environmental permitting and services for all the Stoney Run projects
Project Manager
Kathie Angle
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 19-Mar-2025 31-Dec-2027
47%
PE - Preliminary 02-Nov-2018 02-Nov-2018
100%
PE - Design 03-Nov-2018 03-Nov-2018
100%
PE - Environmental 19-Mar-2025 31-Dec-2027
47%
PE - Scoping 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 11-Nov-2018 11-Nov-2018
100%
CA - Pre-Ad 06-Nov-2018 06-Nov-2018
100%
CA - Advertisement 07-Nov-2018 07-Nov-2018
100%
CA - Bid Date 08-Nov-2018 08-Nov-2018
100%
CA - Construction Award 09-Nov-2018 09-Nov-2018
100%
CA - CEI 10-Nov-2018 10-Nov-2018
100%
CA - Construction 10-Nov-2018 10-Nov-2018
100%
CA - Construction Closeout 11-Nov-2018 11-Nov-2018
100%
Project Closeout 01-Jan-2028 08-Mar-2028

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Stoney Run Environmental Services ATCS, P.L.C 19-Mar-2025 01-Dec-2027 $206,178.49 $129,123.20

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.