Project Description
Project Manager
Carolyn Bowman
Inspector
How does this project serve Newport News’ citizens?
Relationship to Comprehensive Plan Themes
Schedule
| Activity |
Start |
Finish |
% Complete |
| PE - Preliminary |
21-Nov-2024 |
25-Mar-2025 |
|
| PE - Design |
26-Mar-2025 |
09-May-2026 |
|
| PE - Environmental |
26-Mar-2025 |
15-Apr-2026 |
|
| Construction |
10-May-2026 |
14-Aug-2027 |
|
| CA - Pre-Ad |
10-May-2026 |
30-May-2026 |
|
| CA - Advertisement |
31-May-2026 |
29-Jun-2026 |
|
| CA - Bid Date |
30-Jun-2026 |
30-Jun-2026 |
|
| CA - Construction Award |
01-Jul-2026 |
09-Aug-2026 |
|
| CA - CEI |
10-Aug-2026 |
15-Jun-2027 |
|
| CA - Construction |
10-Aug-2026 |
15-Jun-2027 |
|
| CA - Construction Closeout |
16-Jun-2027 |
14-Aug-2027 |
|
| Project Closeout |
15-Aug-2027 |
12-Nov-2027 |
|
Contracts
| Contract Name |
Contractor/Consultant |
Start |
Finish |
Contract Amount |
Paid To Date |
| Professional Services for Seafood Industrial Park Outer Harbor Pier and Dolphins Condition Survey |
MOFFATT AND NICHOL |
21-Nov-2024 |
30-Oct-2025 |
$54,780.00 |
$46,950.00 |
| Professional Services for Seafood Industrial Park Outer Harbor Pier and Dolphins Restoration |
MOFFATT AND NICHOL |
25-Mar-2025 |
31-Mar-2027 |
$145,305.00 |
$31,023.00 |
The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.