Project Description
To resurface 28th Street and associated concrete repairs, including upgrading handicap ramps. Limits are from Jefferson Avenue to Ease of Madison Avenue.
Project Manager
Thomas Cheney
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 30-Jun-2024 14-Mar-2025
100%
PE - Preliminary 30-Jun-2024 17-Jan-2025
100%
PE - Design 18-Jan-2025 12-Feb-2025
100%
PE - Environmental 18-Jan-2025 27-Feb-2025
100%
PE - Scoping 18-Jan-2025 14-Mar-2025
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
Construction 15-Mar-2025 07-Nov-2026
55%
CA - Pre-Ad 15-Mar-2025 15-Mar-2025
100%
CA - Advertisement 16-Mar-2025 16-Mar-2025
100%
CA - Bid Date 17-Mar-2025 17-Mar-2025
100%
CA - Construction Award 01-Jul-2025 01-Jul-2025
100%
CA - CEI 02-Jul-2025 08-Oct-2026
48%
CA - Construction 02-Jul-2025 08-Oct-2026
48%
CA - Construction Closeout 09-Oct-2026 07-Nov-2026
Project Closeout 08-Nov-2026 06-May-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Pavement Marking Plans ATCS, P.L.C 10-Feb-2025 30-Sep-2025 $8,669.42 $8,669.42
SGR25LP 28th St Allan Myers ALLAN MYERS VA, INC. 15-Oct-2025 15-Dec-2025 $123,341.93 $113,147.66
Construction Engineering & Inspection Services CENTURY ENGINEERING, INC 15-Oct-2025 15-Nov-2025 $81,345.20 $40,328.12

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.