Project Description
Resurface Warwick Blvd and make associated concrete repairs, including upgrading handicap ramps, from Colony Road to Oyster P:oint Road.
Project Manager
Thomas Cheney
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 30-Jun-2024 17-Mar-2025
100%
PE - Preliminary 30-Jun-2024 17-Jan-2025
100%
PE - Design 18-Jan-2025 11-Feb-2025
100%
PE - Environmental 18-Jan-2025 05-Mar-2025
100%
PE - Scoping 18-Jan-2025 17-Mar-2025
100%
ROW - Land Acquisition 27-Jan-2025 27-Jan-2025
100%
Construction 18-Mar-2025 30-Nov-2026
62%
CA - Pre-Ad 18-Mar-2025 18-Mar-2025
100%
CA - Advertisement 19-Mar-2025 19-Mar-2025
100%
CA - Bid Date 20-Mar-2025 20-Mar-2025
100%
CA - Construction Award 14-Jul-2025 31-Oct-2025
100%
CA - CEI 15-Jul-2025 31-Oct-2026
57%
CA - Construction 12-Aug-2025 31-Oct-2026
54%
CA - Construction Closeout 01-Nov-2026 30-Nov-2026
Project Closeout 01-Dec-2026 29-May-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Pavement Marking Plans ATCS, P.L.C 10-Feb-2025 30-Sep-2025 $14,625.59 $14,625.59
SGR25LP 1301 WARWICK BOULEVARD BRANSCOME, INC 15-Jul-2025 30-Sep-2025 $840,752.72 $679,626.22
Construction Engineering & Inspection Services CENTURY ENGINEERING, INC 15-Jul-2025 30-Sep-2025 $174,663.36 $74,317.34

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.