Project Description
Annual resurfacing contract for FY25
Project Manager
Thomas Cheney
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 06-May-2024 30-Sep-2024
100%
PE - Preliminary 02-Nov-2018 02-Nov-2018
100%
PE - Design 06-May-2024 30-Sep-2024
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Scoping 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 04-Oct-2024 13-Dec-2025
100%
CA - Pre-Ad 01-Oct-2024 01-Oct-2024
100%
CA - Advertisement 02-Oct-2024 02-Oct-2024
100%
CA - Bid Date 21-Oct-2024 21-Oct-2024
100%
CA - Construction Award 04-Oct-2024 19-Dec-2024
100%
CA - CEI 01-Nov-2024 01-Nov-2024
100%
CA - Construction 17-Mar-2025 13-Nov-2025
100%
CA - Construction Closeout 14-Nov-2025 13-Dec-2025
100%
Project Closeout 14-Dec-2025 28-Dec-2025
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
2025 Annual Resurfacing ALLAN MYERS VA, INC. 15-Nov-2024 30-Jun-2025 $6,798,794.95 $6,549,256.57
Pavement Marking Plans ATCS, P.L.C 10-Feb-2025 30-Sep-2025 $83,379.74 $83,379.74
2025 Annual Citywide Resurfacing Additional Streets ALLAN MYERS VA, INC. 24-Apr-2025 30-Sep-2025 $845,199.93 $820,369.26

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.