Project Description
Project Manager
Bruce Wobser
Inspector
How does this project serve Newport News’ citizens?
Relationship to Comprehensive Plan Themes
Schedule
| Activity |
Start |
Finish |
% Complete |
| PE/Design |
07-May-2024 |
28-Feb-2026 |
|
| PE - Preliminary |
07-May-2024 |
30-Dec-2024 |
|
| PE - Design |
06-Dec-2024 |
28-Feb-2026 |
|
| PE - Environmental |
01-Nov-2025 |
01-Nov-2025 |
|
| PE - Scoping |
01-Nov-2025 |
01-Nov-2025 |
|
| PE - Public Involvement |
01-Nov-2025 |
01-Nov-2025 |
|
| Right of Way |
03-Mar-2025 |
01-Nov-2025 |
|
| ROW - Land Acquisition |
03-Mar-2025 |
01-Nov-2025 |
|
| ROW - Utility Relocation |
03-Mar-2025 |
01-Nov-2025 |
|
| Construction |
17-Mar-2026 |
27-May-2027 |
|
| CA - Pre-Ad |
17-Mar-2026 |
31-May-2026 |
|
| CA - Advertisement |
01-Jun-2026 |
22-Jun-2026 |
|
| CA - Bid Date |
23-Jun-2026 |
23-Jun-2026 |
|
| CA - Construction Award |
24-Jun-2026 |
07-Aug-2026 |
|
| CA - CEI |
08-Aug-2026 |
21-Sep-2026 |
|
| CA - Construction |
22-Sep-2026 |
26-Apr-2027 |
|
| CA - Construction Closeout |
27-Apr-2027 |
27-May-2027 |
|
| Project Closeout |
28-May-2027 |
26-Jun-2027 |
|
Contracts
| Contract Name |
Contractor/Consultant |
Start |
Finish |
Contract Amount |
Paid To Date |
| ARCHITECTUAL AND ENGINEERING SERVICES FOR THE RENOVATION OF RESTAURANT FACILITY LOCATED AT 2295 HARB |
PMA INC |
07-May-2024 |
30-Nov-2024 |
$143,863.00 |
$143,863.00 |
| 2295 Harbor Road - Construction Document Design |
PMA INC |
06-Dec-2024 |
31-May-2025 |
$566,146.00 |
$369,918.55 |
The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.