Project Description
Project Manager
Bruce Wobser
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 07-May-2024 28-Feb-2026
100%
PE - Preliminary 07-May-2024 30-Dec-2024
100%
PE - Design 06-Dec-2024 28-Feb-2026
100%
PE - Environmental 01-Nov-2025 01-Nov-2025
100%
PE - Scoping 01-Nov-2025 01-Nov-2025
100%
PE - Public Involvement 01-Nov-2025 01-Nov-2025
100%
Right of Way 03-Mar-2025 01-Nov-2025
100%
ROW - Land Acquisition 03-Mar-2025 01-Nov-2025
100%
ROW - Utility Relocation 03-Mar-2025 01-Nov-2025
100%
Construction 17-Mar-2026 27-May-2027
5%
CA - Pre-Ad 17-Mar-2026 31-May-2026
33%
CA - Advertisement 01-Jun-2026 22-Jun-2026
CA - Bid Date 23-Jun-2026 23-Jun-2026
CA - Construction Award 24-Jun-2026 07-Aug-2026
CA - CEI 08-Aug-2026 21-Sep-2026
CA - Construction 22-Sep-2026 26-Apr-2027
CA - Construction Closeout 27-Apr-2027 27-May-2027
Project Closeout 28-May-2027 26-Jun-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
ARCHITECTUAL AND ENGINEERING SERVICES FOR THE RENOVATION OF RESTAURANT FACILITY LOCATED AT 2295 HARB PMA INC 07-May-2024 30-Nov-2024 $143,863.00 $143,863.00
2295 Harbor Road - Construction Document Design PMA INC 06-Dec-2024 31-May-2025 $566,146.00 $369,918.55

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.