Project Description
Project Manager
Hai Tran
Inspector
How does this project serve Newport News’ citizens?
Relationship to Comprehensive Plan Themes
Schedule
| Activity |
Start |
Finish |
% Complete |
| PE/Design |
02-Nov-2018 |
31-Jul-2025 |
|
| PE - Preliminary |
02-Nov-2018 |
30-May-2024 |
|
| PE - Design |
03-Jun-2024 |
31-Jul-2025 |
|
| PE - Environmental |
05-Nov-2018 |
05-Nov-2018 |
|
| PE - Scoping |
01-Mar-2024 |
31-May-2024 |
|
| PE - Public Involvement |
05-Nov-2018 |
05-Nov-2018 |
|
| Right of Way |
05-Nov-2018 |
05-Nov-2018 |
|
| ROW - Land Acquisition |
05-Nov-2018 |
05-Nov-2018 |
|
| ROW - Utility Relocation |
05-Nov-2018 |
05-Nov-2018 |
|
| Construction |
01-Sep-2025 |
23-Jan-2026 |
|
| CA - Pre-Ad |
01-May-2025 |
15-May-2025 |
|
| CA - Advertisement |
16-May-2025 |
30-May-2025 |
|
| CA - Bid Date |
01-Jul-2025 |
02-Jul-2025 |
|
| CA - Construction Award |
03-Jul-2025 |
03-Jul-2025 |
|
| CA - CEI |
01-Sep-2025 |
01-Sep-2025 |
|
| CA - Construction |
02-Sep-2025 |
22-Dec-2025 |
|
| CA - Construction Closeout |
23-Dec-2025 |
23-Jan-2026 |
|
| Project Closeout |
24-Jan-2026 |
24-Jan-2026 |
|
Comments
Per VDOT as of 2/19/25, they still waiting to clear the project in the area before moving forward with the dredging. 02/21/2026
Contracts
| Contract Name |
Contractor/Consultant |
Start |
Finish |
Contract Amount |
Paid To Date |
| Olive Drive Drainage Improvements |
Johnson, Mirmiran & Thompson, Inc. |
31-May-2024 |
31-Aug-2025 |
$117,438.49 |
$74,215.07 |
The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.