Project Description
Project Manager
Hai Tran
Inspector
How does this project serve Newport News’ citizens?
Relationship to Comprehensive Plan Themes
Schedule
| Activity |
Start |
Finish |
% Complete |
| PE/Design |
03-Jun-2024 |
28-Feb-2028 |
|
| PE - Preliminary |
03-Jun-2024 |
13-Jan-2025 |
|
| PE - Design |
14-Jan-2025 |
28-Feb-2028 |
|
| Project Closeout |
01-Dec-2027 |
31-Dec-2027 |
|
Comments
Meeting to review link-node diagram was conducted on 2/20/25. JMT is now moving toward subbasins delineation and SWMM modeling. 02/21/2026
Contracts
| Contract Name |
Contractor/Consultant |
Start |
Finish |
Contract Amount |
Paid To Date |
| Deep Creek Watershed Study |
Johnson, Mirmiran & Thompson, Inc. |
13-Dec-2024 |
28-Feb-2028 |
$364,165.90 |
$108,220.27 |
The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.