Project Description
The project involves addition of 10’ SUP for an existing trail in Newport News Park starting from the park camp office connecting to the park bikeway for the distance of 2.5 miles. No railroad impacts are anticipated.
Project Manager
Thomas Cheney
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 01-Oct-2025 30-Dec-2026
62%
PE - Preliminary 01-Oct-2025 01-Oct-2025
100%
PE - Design 02-Oct-2025 02-Oct-2025
100%
PE - Environmental 09-Oct-2025 30-Dec-2026
61%
PE - Scoping 09-Oct-2025 21-Feb-2026
100%
PE - Public Involvement 02-May-2026 02-Aug-2026
78%
Right of Way 23-Jun-2026 01-Oct-2026
20%
ROW - Land Acquisition 23-Jun-2026 02-Aug-2026
50%
ROW - Utility Relocation 23-Jun-2026 01-Oct-2026
20%
Construction 31-Dec-2026 07-Dec-2027
CA - Pre-Ad 31-Dec-2026 31-Dec-2026
CA - Advertisement 01-Jan-2027 11-Jan-2027
CA - Bid Date 12-Jan-2027 31-Jan-2027
CA - Construction Award 01-Feb-2027 25-Feb-2027
CA - CEI 26-Feb-2027 26-Feb-2027
CA - Construction 26-Feb-2027 26-Feb-2027
CA - Construction Closeout 27-Feb-2027 07-Dec-2027
Project Closeout 08-Dec-2027 06-Mar-2028

Comments

Scope & Fee is not finalized yet. Still waiting for City to decide which Spur (connection to Taril757 segments) should be added to the Scope. 03/05/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.