Project Description
This is a federally funded Smart Scale project to design and construct a third through westbound lane on Oyster Point Road from Warwick Boulevard to Arboretum Way, as well as a through eastbound lane between Nettles Lane and Arboretum Way, associated pedestrian accommodations and signal timing improvements.
Project Manager
Ioana Verde
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 04-Aug-2025 08-Aug-2028
22%
PE - Preliminary 04-Aug-2025 30-Jun-2026
75%
PE - Design 01-Jul-2026 08-Aug-2028
PE - Environmental 28-Nov-2026 28-May-2027
PE - Scoping 27-Aug-2027 24-Nov-2027
PE - Public Involvement 29-May-2027 26-Aug-2027
Right of Way 09-Aug-2028 08-Aug-2030
ROW - Land Acquisition 09-Aug-2028 08-Aug-2030
ROW - Utility Relocation 09-Aug-2028 08-Aug-2030
Construction 09-Aug-2030 20-Jun-2032
CA - Pre-Ad 09-Aug-2030 22-Aug-2030
CA - Advertisement 23-Aug-2030 21-Sep-2030
CA - Bid Date 22-Sep-2030 22-Sep-2030
CA - Construction Award 23-Sep-2030 22-Oct-2030
CA - CEI 23-Oct-2030 21-Apr-2032
CA - Construction 23-Oct-2030 21-Apr-2032
CA - Construction Closeout 22-Apr-2032 20-Jun-2032
Project Closeout 21-Jun-2032 20-Jun-2033

Comments

Consultant selection in progress. Consultant working on proposal revisions per City comments. 12/23/2025

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.