Project Description
Location: Up to 79 intersections throughout the city. Funding will probably allow for about 50.
Project Manager
Jennifer Butler
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Oct-2024 15-Sep-2026
87%
PE - Preliminary 01-Oct-2024 13-May-2025
100%
PE - Design 14-May-2025 15-Sep-2026
81%
PE - Environmental 14-May-2025 31-Mar-2026
100%
PE - Scoping 14-May-2025 17-Dec-2025
100%
PE - Public Involvement 14-May-2025 31-Mar-2026
100%
Right of Way 16-Sep-2026 15-Sep-2027
ROW - Land Acquisition 16-Sep-2026 15-Sep-2027
ROW - Utility Relocation 16-Sep-2026 15-Sep-2027
Construction 16-Sep-2027 21-Sep-2027
CA - Pre-Ad 16-Sep-2027 16-Sep-2027
CA - Advertisement 17-Sep-2027 17-Sep-2027
CA - Bid Date 18-Sep-2027 18-Sep-2027
CA - Construction Award 19-Sep-2027 19-Sep-2027
CA - CEI 20-Sep-2027 20-Sep-2027
CA - Construction 20-Sep-2027 20-Sep-2027
CA - Construction Closeout 21-Sep-2027 21-Sep-2027
Project Closeout 22-Sep-2027 22-Sep-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
123150 Citywide Ped Impr Design Johnson, Mirmiran & Thompson, Inc. 13-May-2025 31-Dec-2028 $1,370,913.32 $1,031,006.71

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.