Project Description
Project Manager
Ivy Stroud
757-926-3668
wobserbd@nnva.gov
Inspector
George Batts
battsgj@nnva.gov

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 09-Jan-2023 01-Sep-2025
100%
PE - Preliminary 09-Jan-2023 16-Jul-2024
100%
PE - Design 17-Jul-2024 29-Aug-2025
100%
PE - Environmental 30-Aug-2025 30-Aug-2025
100%
PE - Scoping 31-Aug-2025 31-Aug-2025
100%
PE - Public Involvement 01-Sep-2025 01-Sep-2025
100%
Right of Way 02-Sep-2025 04-Sep-2025
100%
ROW - Land Acquisition 02-Sep-2025 02-Sep-2025
100%
ROW - Utility Relocation 03-Sep-2025 04-Sep-2025
100%
Construction 05-Sep-2025 18-Aug-2027
35%
CA - Pre-Ad 05-Sep-2025 13-Nov-2025
100%
CA - Advertisement 14-Nov-2025 08-Jan-2026
100%
CA - Bid Date 09-Jan-2026 09-Jan-2026
100%
CA - Construction Award 10-Jan-2026 05-Mar-2026
100%
CA - CEI 06-Mar-2026 06-Mar-2026
100%
CA - Construction 07-Mar-2026 19-Jul-2027
13%
CA - Construction Closeout 20-Jul-2027 18-Aug-2027
Project Closeout 19-Aug-2027 16-Dec-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Municipal Building 2 Courtrooms BURGESS & NIPLE, INC 16-Jul-2024 16-Jul-2025 $1,031,751.00 $869,522.20
Municipal BLDG Courtrooms GC Commercial 16-Mar-2026 12-Oct-2026 $6,978,954.73 $62,225.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.